TABS2025000574New ConstructionReview CompletePrivate
Dfw III-III Building 7
540 Austin Bvld, Red Oak TX 75154
Dfw III-III Building 7 is a privately funded new construction project at 540 Austin Bvld in Red Oak, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on September 10, 2024 as TABS2025000574. The filing lists 251,815 square feet and an estimated cost of $100M. Work is scheduled to start June 20, 2024 and to finish June 4, 2027. Current status: Review Complete.
- Estimated cost
- $100M
- Square feet
- 251,815
- Start
- Jun 20, 2024
- Completion
- Jun 4, 2027
Scope of work
Construction of a new data center on a datacenter campus.
Project details
TABS project numberTABS2025000574
FacilityBuilding 7
Location540 Austin Bvld, Red Oak, TX 75154
CountyEllis County
Type of workNew Construction
FundingThis project is privately funded, on private land for private use.
Tenant fundedNo
RegisteredSeptember 10, 2024
StatusReview Complete
OwnerCompass Datacenters Dfw Iiig LLC
Tenant Pro
Design firm & contacts Pro
Other TDLR projects in 75154
- Mccowan Ms - Desoto ISDTABS2027004674 · Oct 28, 2026 · $4.0M
- Compass Datacenters - Dfwiii-III - Building 8 - Interior / Tenant Fit OutTABS2027003683 · Oct 15, 2026 · $100M
- Compass Datacenters - Dfwiii-III - Building 10 - Interior / Tenant Fit OutTABS2027003697 · Oct 15, 2026 · $100M
- Compass Datacenters - Dfwiii-III - Building 9 - Interior / Tenant Fit OutTABS2027003693 · Oct 15, 2026 · $100M
- Red2aTABS2027003112 · Oct 8, 2026 · $176M
- Databank Red Oak - Dfw15 Base BuildingTABS2027000733 · Sep 10, 2026 · $425M
- Databank Red Oak - Dfw14 Base BuildingTABS2026027681 · Aug 12, 2026 · $325M
- Shine PediatricsTABS2026026459 · Jul 29, 2026 · $71K