TABS2025005662New ConstructionReview CompletePrivate
Firestone Complete Auto Care - Red Oak, TX
E. Ovilla Rd, Red Oak TX 75154
Firestone Complete Auto Care - Red Oak, TX is a privately funded new construction project at E. Ovilla Rd in Red Oak, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on November 15, 2024 as TABS2025005662. The filing lists 6,607 square feet and an estimated cost of $2.5M. Work is scheduled to start March 1, 2025 and to finish December 1, 2025. Current status: Review Complete.
- Estimated cost
- $2.5M
- Square feet
- 6,607
- Start
- Mar 1, 2025
- Completion
- Dec 1, 2025
Scope of work
A ground-up construction of a 6,607 SF Firestone Complete Auto Care Facility.
Project details
TABS project numberTABS2025005662
FacilityFirestone Complete Auto Care
LocationE. Ovilla Rd, Red Oak, TX 75154
CountyEllis County
Type of workNew Construction
FundingThis project is privately funded, on private land for private use.
Tenant fundedNo
RegisteredNovember 15, 2024
StatusReview Complete
OwnerFcac - Red Oak, LLC
TenantPhilip Ormsby
Design firm & contacts Pro
Other TDLR projects in 75154
- Mccowan Ms - Desoto ISDTABS2027004674 · Oct 28, 2026 · $4.0M
- Compass Datacenters - Dfwiii-III - Building 9 - Interior / Tenant Fit OutTABS2027003693 · Oct 15, 2026 · $100M
- Compass Datacenters - Dfwiii-III - Building 10 - Interior / Tenant Fit OutTABS2027003697 · Oct 15, 2026 · $100M
- Compass Datacenters - Dfwiii-III - Building 8 - Interior / Tenant Fit OutTABS2027003683 · Oct 15, 2026 · $100M
- Red2aTABS2027003112 · Oct 8, 2026 · $176M
- Databank Red Oak - Dfw15 Base BuildingTABS2027000733 · Sep 10, 2026 · $425M
- Databank Red Oak - Dfw14 Base BuildingTABS2026027681 · Aug 12, 2026 · $325M
- Shine PediatricsTABS2026026459 · Jul 29, 2026 · $71K