TABS2025014134Renovation/AlterationProject ClosedPublic funds
Copa Transit Bus Pads #3
Rights-Of Way Throughout, Port Arthur, Teaxas, Port Arthur TX 77640
Copa Transit Bus Pads #3 is a publicly funded renovation / alteration project at Rights-Of Way Throughout, Port Arthur, Teaxas in Port Arthur, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on March 13, 2025 as TABS2025014134. The filing lists 2,100 square feet and an estimated cost of $200K. Work is scheduled to start May 31, 2025 and to finish August 15, 2025. Current status: Project Closed.
- Estimated cost
- $200K
- Square feet
- 2,100
- Start
- May 31, 2025
- Completion
- Aug 15, 2025
Scope of work
Installation of bus pads in developed public right-of-way. Some pad sites will be removed/replaced and some new. Some pads will tie into existing sidewalk/ramps and some will be new, Design follows PROWAG as required- federally funded
Project details
TABS project numberTABS2025014134
FacilityCity Of Port Arthurtransit -Rights-Of-Way
Locationrights-of way throughout, Port Arthur, Teaxas, Port Arthur, TX 77640
CountyJefferson County
Type of workRenovation/Alteration
FundingThis project involves public funds, public land, or is a Federally funded roadway project.
Tenant fundedNo
RegisteredMarch 13, 2025
StatusProject Closed
OwnerCity Of Port Arthur
Tenant Pro
Design firm & contacts Pro
Other TDLR projects in 77640
- Lincoln Park EnhancementsTABS2027004558 · Oct 27, 2026 · $100K
- City Of Pa Pleasure Island Club HouseTABS2027003898 · Oct 19, 2026 · $2.5M
- Renovations To Suite 140TABS2027003527 · Oct 14, 2026 · $210K
- Motiva Fire Station RenovationTABS2026028079 · Aug 18, 2026 · $5.0M
- Photography Studio/SubwayTABS2026026860 · Aug 4, 2026 · $50K
- Turn Lane And Truck Staging AreaTABS2026025944 · Jul 23, 2026 · $3.5M
- Adams Historic RenovationTABS2026025865 · Jul 22, 2026 · $60M
- Rose Hill ParkTABS2026025321 · Jul 15, 2026 · $4.4M