TABS2025017762New ConstructionReview CompletePrivate
Frassati Catholic High School - New Classroom Building
22151 Frassati Way, Spring TX 77389
Frassati Catholic High School - New Classroom Building is a privately funded new construction project at 22151 Frassati Way in Spring, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on April 29, 2025 as TABS2025017762. The filing lists 20,019 square feet and an estimated cost of $7.0M. Work is scheduled to start October 6, 2025 and to finish August 6, 2026. Current status: Review Complete.
- Estimated cost
- $7.0M
- Square feet
- 20,019
- Start
- Oct 6, 2025
- Completion
- Aug 6, 2026
Scope of work
THE PROJECT IS A NEW CLASSROOM BUILDING AS AN ADDITION TO THE EXISTING FRASSATI CATHOLIC HIGH SCHOOL CAMPUS. THE BUILDING CONSISTS OF (7) CLASSROOMS, (3) LABS WITH (2) PREP ROOMS, AND AN ADMINISTRATIVE SUITE
Project details
TABS project numberTABS2025017762
FacilityFrassati Catholic High School - New Classroom Building
Location22151 Frassati Way, Spring, TX 77389
CountyHarris County
Type of workNew Construction
FundingThis project is privately funded, on private land for private use.
Tenant fundedNo
RegisteredApril 29, 2025
StatusReview Complete
OwnerFrassati Catholic High School
Tenant Pro
Design firm & contacts Pro
Other TDLR projects in 77389
- Gosling Oaks - Building 1TABS2027005288 · Nov 5, 2026 · $750K
- Emhc ResiliencyTABS2027004997 · Nov 3, 2026 · $75M
- Iron Oak Energy - Level 2 ExpansionTABS2027002634 · Oct 2, 2026 · $1.1M
- Alta Gosling RoadTABS2027002465 · Oct 1, 2026 · $1.5M
- Emhc Energy 4 Ups UpgradeTABS2027001235 · Sep 17, 2026 · $1.4M
- Willow Creek Village LandscapeTABS2027001053 · Sep 15, 2026 · $400K
- Pepper Lunch, Spring, TXTABS2026029177 · Aug 31, 2026 · $850K
- Champion Fiberglass - 80 X 180 Auxiliary BuildingTABS2026028092 · Aug 18, 2026 · $927K