TABS2025021895New ConstructionReview CompletePublic funds
Howard Lane / Center Line Pass / The Lakes Blvd Intersection Improvements
Howard Lane And Center Line Pass/The Lakes Blvd, Austin TX 78753
Howard Lane / Center Line Pass / The Lakes Blvd Intersection Improvements is a publicly funded new construction project at Howard Lane And Center Line Pass/The Lakes Blvd in Austin, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on June 24, 2025 as TABS2025021895. The filing lists 17,613 square feet and an estimated cost of $1.6M. Work is scheduled to start January 15, 2027 and to finish September 14, 2027. Current status: Review Complete.
- Estimated cost
- $1.6M
- Square feet
- 17,613
- Start
- Jan 15, 2027
- Completion
- Sep 14, 2027
Scope of work
Safety improvements including new sidewalk and curb ramps, pedestrian signal infrastructure, modifications to the right turn slip lane at Center Line Pass including installation of new signal, and median improvements. (17,613 SF)
Project details
TABS project numberTABS2025021895
FacilityN/A
LocationHoward Lane and Center Line Pass/The Lakes Blvd., Austin, TX 78753
CountyTravis County
Type of workNew Construction
FundingThis project involves public funds, public land, or is a Federally funded roadway project.
Tenant fundedNo
RegisteredJune 24, 2025
StatusReview Complete
OwnerCity Of Austin
Tenant Pro
Design firm & contacts Pro
Other TDLR projects in 78753
- IH 35 (csj: 0015-13-437)TABS2027005249 · Nov 5, 2026 · $2.7M
- Alliance – 8522 Connor Lane Suite 150TABS2027005019 · Nov 3, 2026 · $246K
- Discount TireTABS2027005028 · Nov 3, 2026 · $310K
- 1001 W Howard Lane - Storage LotTABS2027004782 · Oct 30, 2026 · $5.0M
- Mitchell Time And Parking Main OfficeTABS2027004105 · Oct 21, 2026 · $638K
- Pce TechnologyTABS2027003144 · Oct 8, 2026 · $350K
- Asme Phase 2 - Building BTABS2027002411 · Sep 30, 2026 · $450K
- Clearwater Express - N LamarTABS2027002395 · Sep 30, 2026 · $1.3M