TABS2026002290New ConstructionReview CompletePublic funds
Wilbarger Creek Wastewater Treatment Plant Expansion
547 Llano Street, Manor TX 78653
Wilbarger Creek Wastewater Treatment Plant Expansion is a publicly funded new construction project at 547 Llano Street in Manor, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on October 1, 2025 as TABS2026002290. The filing lists 3,800 square feet and an estimated cost of $1.2M. Work is scheduled to start December 1, 2025 and to finish December 1, 2027. Current status: Review Complete.
- Estimated cost
- $1.2M
- Square feet
- 3,800
- Start
- Dec 1, 2025
- Completion
- Dec 1, 2027
Scope of work
New sludge building for a wastewater treatment plant.
Project details
TABS project numberTABS2026002290
FacilityWilbarger Sludge Building
Location547 Llano Street, Manor, TX 78653
CountyTravis County
Type of workNew Construction
FundingThis project involves public funds, public land, or is a Federally funded roadway project.
Tenant fundedNo
RegisteredOctober 1, 2025
StatusReview Complete
OwnerCity Of Manor Public Works Department
Tenant Pro
Design firm & contacts Pro
Other TDLR projects in 78653
- Briarwood Phase 3TABS2027004562 · Oct 27, 2026 · $7.6M
- Hobby Lobby ManorTABS2027002734 · Oct 5, 2026 · $6.0M
- Shell BuildingTABS2027001160 · Sep 16, 2026 · $1.3M
- Hiland Dairy FoodsTABS2027000370 · Sep 4, 2026 · $1.2M
- The Toasted Yolk - ManorTABS2027000410 · Sep 4, 2026 · $850K
- Academy Sports + OutdoorsTABS2026029094 · Aug 28, 2026 · $6.0M
- Firehouse Subs Las EntradasTABS2026028389 · Aug 20, 2026 · $650K
- FM 973 Center Bldg. Two - Unoccupied ShellTABS2026027734 · Aug 13, 2026 · $476K