Project Lion is a privately funded new construction project at 2700 FM 1405 in Baytown, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on October 14, 2025 as TABS2026003365. The filing lists 43,358 square feet and an estimated cost of $103M. Work is scheduled to start March 6, 2026 and to finish March 1, 2027. Current status: Review Complete.
- Estimated cost
- $103M
- Square feet
- 43,358
- Start
- Mar 6, 2026
- Completion
- Mar 1, 2027
Scope of work
The project consists of an electrolyte production facility including warehouse space, an office and lab building, loading and unloading station, tank farm and guard houses at the north and south site entry points.
Project details
TABS project numberTABS2026003365
FacilityProject Lion
Location2700 FM 1405, Baytown, TX 77523
CountyChambers County
Type of workNew Construction
FundingThis project is privately funded, on private land for private use.
Tenant fundedNo
RegisteredOctober 14, 2025
StatusReview Complete
OwnerTinci Delaware, LLC
Tenant Pro
Design firm & contacts Pro
Everything filed at 2700 FM 1405
This is the only filing on record here so far. Follow the address to hear about new permits.
See the address historyOther TDLR projects in 77523
- WalmartTABS2027005878 · Nov 15, 2026 · $16M
- WalmartTABS2027005875 · Nov 15, 2026 · $12M
- WalmartTABS2027005880 · Nov 15, 2026 · $16M
- Brookstone Professional OffficeTABS2027005424 · Nov 9, 2026 · $1.3M
- Hotworx StudioTABS2027004162 · Oct 21, 2026 · $117K
- Jotun Paint T.i.TABS2027003420 · Oct 13, 2026 · $1.9M
- Eoc 25054 Baytown, TexasTABS2027001937 · Sep 25, 2026 · $1.8M
- Barbers Hill Middle School North Locker Room Renovation (package C )TABS2027001403 · Sep 18, 2026 · $7.0M