TABS2026004022New ConstructionInspection CompletePublic funds
Pearl South Bridge Metal Stair
217 Newell Ave, San Antonio TX 78215
Pearl South Bridge Metal Stair is a publicly funded new construction project at 217 Newell Ave in San Antonio, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on October 22, 2025 as TABS2026004022. The filing lists 2,000 square feet and an estimated cost of $500K. Work is scheduled to start November 30, 2025 and to finish November 30, 2026. Current status: Inspection Complete.
- Estimated cost
- $500K
- Square feet
- 2,000
- Start
- Nov 30, 2025
- Completion
- Nov 30, 2026
Scope of work
Constructing a metal stair on the east side of the bridge to get pedestrians from Riverwalk level to parking lot level. Adding flatwork to connect to existing bridge landing.
Project details
TABS project numberTABS2026004022
FacilityPearl South Bridge Metal Stair
Location217 Newell Ave, San Antonio, TX 78215
CountyBexar County
Type of workNew Construction
FundingThis project involves public funds, public land, or is a Federally funded roadway project.
Tenant fundedNo
RegisteredOctober 22, 2025
StatusInspection Complete
OwnerRio Perla Properties LP
Tenant Pro
Design firm & contacts Pro
Other TDLR projects in 78215
- Steptoe & Johnson, PllcTABS2027003744 · Oct 16, 2026 · $215K
- Ok Tours 701 Austin St. Bldg. RenovationTABS2027003702 · Oct 15, 2026 · $725K
- Spec Office - Terrace LevelTABS2027001402 · Sep 18, 2026 · $147K
- Cobra ElectricTABS2027001177 · Sep 16, 2026 · $250K
- Suite 610TABS2027000034 · Sep 1, 2026 · $184K
- Ave. A RetailTABS2026027893 · Aug 14, 2026 · $4.4M
- Avenue A RetailTABS2026027872 · Aug 14, 2026 · $5.9M
- Avenue A RetailTABS2026027900 · Aug 14, 2026 · $602K