TABS2026014368New ConstructionReview CompletePrivate
Homebound Group Wastewater Treatment Plant
US 380 And Red Creek Road, Haskell TX 79521
Homebound Group Wastewater Treatment Plant is a privately funded new construction project at US 380 And Red Creek Road in Haskell, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on March 6, 2026 as TABS2026014368. The filing lists 1,645 square feet and an estimated cost of $12M. Work is scheduled to start August 3, 2026 and to finish November 1, 2027. Current status: Review Complete.
- Estimated cost
- $12M
- Square feet
- 1,645
- Start
- Aug 3, 2026
- Completion
- Nov 1, 2027
Scope of work
A new 1,645 SF wastewater treatment plant with a blower room, electrical room, storage room, and small lab for water quality testing.
Project details
TABS project numberTABS2026014368
FacilityHomebound Group Wastewater Treatment Plant
LocationUS 380 and Red Creek Road, Haskell, TX 79521
CountyHaskell County
Type of workNew Construction
FundingThis project is privately funded, on private land for private use.
Tenant fundedNo
RegisteredMarch 6, 2026
StatusReview Complete
OwnerHomebound Group, LLC
Tenant Pro
Design firm & contacts Pro
Other TDLR projects in 79521
- Quantum Solar II O&mTABS2027004008 · Oct 20, 2026 · $1.0M
- Journey 2aTABS2026023839 · Jun 25, 2026 · $400M
- Journey 1aTABS2026023821 · Jun 25, 2026 · $400M
- Chicken Express HaskellTABS2026016814 · Apr 3, 2026 · $1.5M
- Homebound Group Water Treatment Plant And Fire Protection SystemTABS2026014288 · Mar 5, 2026 · $12M
- Data Center Thm1aTABS2025019833 · May 27, 2025 · $350M
- Miller Branch SolarTABS2025019756 · May 26, 2025 · $1.0M