Washington High School Phase 1 is a publicly funded new construction project at 507 Dr. Martin Luther King Jr. Place N in Conroe, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on April 20, 2026 as TABS2026018099. The filing lists 114,000 square feet and an estimated cost of $40M. Work is scheduled to start August 1, 2026 and to finish December 30, 2027. Current status: Review Complete.

Estimated cost
$40M
Square feet
114,000
Start
Aug 1, 2026
Completion
Dec 30, 2027

Scope of work

Phase 1 of the project consists of the demolition of an existing gym and construction of a new public high school for Conroe ISD on a previously developed site. Work includes the construction of two-story permanent instructional and support spaces.

Project details

TABS project numberTABS2026018099
FacilityWashington High School
Location507 Dr. Martin Luther King Jr. Place N., Conroe, TX 77301
CountyMontgomery County
Type of workNew Construction
FundingThis project involves public funds, public land, or is a Federally funded roadway project.
Tenant fundedNo
RegisteredApril 20, 2026
StatusReview Complete
OwnerConroe ISD
Tenant Pro
Design firm & contacts Pro

Everything filed at 507 Dr. Martin Luther King Jr. Place N

This is the only filing on record here so far. Follow the address to hear about new permits.

See the address history

Other TDLR projects in 77301