TABS2026026411New ConstructionInspection CompletePublic funds

Marron Park Way Paving, Drainage, And Pedestrian Improvements Phase 1

Marron Park Way – From Drennan Street To Maplewood, Houston TX 77012

Marron Park Way Paving, Drainage, And Pedestrian Improvements Phase 1 is a publicly funded new construction project at Marron Park Way – From Drennan Street To Maplewood in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on July 28, 2026 as TABS2026026411. The filing lists 232,000 square feet and an estimated cost of $2.7M. Work is scheduled to start March 20, 2025 and to finish August 1, 2026. Current status: Inspection Complete.

Estimated cost
$2.7M
Square feet
232,000
Start
Mar 20, 2025
Completion
Aug 1, 2026

Scope of work

Roadway paving, drainage, pedestrian (ADA) improvements, North York left-turn lane construction, utility adjustments, pavement markings, signage, street lighting, and associated site restoration.

Project details

TABS project numberTABS2026026411
FacilityMarron Park Way – Phase 1
LocationMarron Park Way – From Drennan Street to Maplewood, Houston, TX 77012
CountyHarris County
Type of workNew Construction
FundingThis project involves public funds, public land, or is a Federally funded roadway project.
Tenant fundedNo
RegisteredJuly 28, 2026
StatusInspection Complete
OwnerCity Of Houston
Tenant Pro
Design firm & contacts Pro