groundranger
TABS2027000730New ConstructionReview CompletePublic funds

FM 518 And Wesley St Drainage Improvements Phase II

FM 518 And Wesley Street, League City TX 77573

FM 518 And Wesley St Drainage Improvements Phase II is a publicly funded new construction project at FM 518 And Wesley Street in League City, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on September 10, 2026 as TABS2027000730. The filing lists 51,900 square feet and an estimated cost of $3.6M. Work is scheduled to start January 18, 2027 and to finish August 20, 2027. Current status: Review Complete.

Estimated cost
$3.6M
Square feet
51,900
Start
Jan 18, 2027
Completion
Aug 20, 2027

Scope of work

Project generally consists of removing and replacing sections of existing roadway, and walkways & ramps (340 SF), installing storm sewer lines, inlets, and manholes, installing water line offsets as necessary, and regrading swales/ditches.

Project details

TABS project numberTABS2027000730
FacilityFM 518 And Wesley Street Public Improvement Project
LocationFM 518 and Wesley Street, League City, TX 77573
CountyGalveston County
Type of workNew Construction
FundingThis project involves public funds, public land, or is a Federally funded roadway project.
Tenant fundedNo
RegisteredSeptember 10, 2026
StatusReview Complete
OwnerCity Of League City
Tenant Pro
Design firm & contacts Pro