TABS2027002676New ConstructionReview CompletePublic funds
Tirz 9 - S Post Oak Sidewalk Maintenance
Along South Post Oak From West Orem To Allum Road, Houston TX 77042
Tirz 9 - S Post Oak Sidewalk Maintenance is a publicly funded new construction project at Along South Post Oak From West Orem To Allum Road in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on October 2, 2026 as TABS2027002676. The filing lists 21,000 square feet and an estimated cost of $400K. Work is scheduled to start January 4, 2027 and to finish May 3, 2027. Current status: Review Complete.
- Estimated cost
- $400K
- Square feet
- 21,000
- Start
- Jan 4, 2027
- Completion
- May 3, 2027
Scope of work
Sidewalk Maintenance along South Post Oak North bound from West Orem to Allum Road
Project details
TABS project numberTABS2027002676
FacilitySidewalk Maintenance Along South Post Oak Road
LocationAlong South post oak from West Orem to Allum Road, Houston, TX 77042
CountyHarris County
Type of workNew Construction
FundingThis project involves public funds, public land, or is a Federally funded roadway project.
Tenant fundedNo
RegisteredOctober 2, 2026
StatusReview Complete
OwnerCity Of Houston Tirz 9
Tenant Pro
Design firm & contacts Pro
Other TDLR projects in 77042
- US Anesthesia PartnersTABS2027005628 · Nov 11, 2026 · $500K
- Alief Clodine Intersections And Sidewalk ImprovementsTABS2027004088 · Oct 21, 2026 · $1.5M
- Meriton Tas HoustonTABS2027003984 · Oct 20, 2026 · $8.6M
- Thermal Engineering International - ExpansionTABS2027003879 · Oct 19, 2026 · $100K
- Level 11 Lobby, Corridor And Restroom RemodelTABS2027003750 · Oct 16, 2026 · $400K
- Hilton Houston Westchase GuestroomsTABS2027003415 · Oct 13, 2026 · $17M
- Pelican Energy Partners - Lease Expansion / RenovationTABS2027001979 · Sep 25, 2026 · $800K
- Tran Law GroupTABS2027001930 · Sep 24, 2026 · $123K