Expired permits listed for chiller replacement

City of Austin records list chiller replacement work at 100 E 27th St. A building permit was filed August 4, 2025, and a mechanical permit followed on August 6; both are marked expired.

Summarized from City of Austin records · updated Aug 6, 2025

Projects
4
4 filings
Latest filing
Aug 6, 2025
since Jan 8, 2024
Largest scope
—
Listed value
—

Permit & project history

4 projects
  1. Chiller replacement

    Chiller replacement

    City of Austin permitMechanical PermitExpired
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. Chiller replacement

    Chiller replacement

    City of Austin permitBuilding PermitExpired
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. Installation of roof mounted (ballasted) solar electric system on the roof of the mcmillan building at the austin presbyterian theological seminary campus. electrical interconnection will be at the mccord building

    Installation of roof mounted (ballasted) solar electric system on the roof of the mcmillan building at the austin presbyterian theological seminary campus. electrical interconnection will be at the mccord building

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  4. Installation of roof mounted (ballasted) solar electric system on the roof of the mcmillan building at the austin presbyterian theological seminary campus. electrical interconnection will be at the mccord building

    Installation of roof mounted (ballasted) solar electric system on the roof of the mcmillan building at the austin presbyterian theological seminary campus. electrical interconnection will be at the mccord building

    City of Austin permitBuilding PermitExpired
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Austin

Questions about 100 E 27th St

What work was permitted at 100 E 27th St in Austin?

City of Austin permit records describe the work as chiller replacement.

When were the chiller replacement permits filed?

The building permit, 2025-093474 BP, was filed August 4, 2025. The mechanical permit, 2025-093474 MP, was filed August 6, 2025.

Are the permits for 100 E 27th St still active?

No. The City of Austin records list both permits as expired.

Is a new building being built at 100 E 27th St?

The records describe chiller replacement, not construction of a new building.

What is the status of the chiller replacement project at 100 E 27th St?

The City of Austin records show two permits for chiller replacement, and both have expired.

Also being built nearby

All of 78712

More solar installs in 78712.

Get alerts for 100 E 27th St