groundranger
Recent · latest filing Aug 2026Commercial

230 Eaglewood

Boling, TX 77420 · Amazon Data Services, INC

Project Eagle data center registered for construction

A 189,060-square-foot data center, identified as Building G, is registered for new construction at 230 Eaglewood in Boling. The Texas Department of Licensing and Regulation record for Project Eagle was filed August 5, 2026, and lists an estimated project cost of $300 million.

Summarized from Texas Department of Licensing and Regulation records · updated Aug 5, 2026

Projects
1
1 filings
Latest filing
Aug 5, 2026
since Aug 5, 2026
Largest scope
189,060 sf
Estimated cost
$300M
state registration

Permit & project history

1 project
  1. Project Eagle

    Data center — building g

    TDLR project registrationNew ConstructionProject Registered189,060 sq ft$300M est.
    Tenant / owner
    Project Eagle
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 230 Eaglewood

What is being built at 230 Eaglewood in Boling?

A 189,060-square-foot data center identified as Building G is registered for new construction at the address.

Who is behind the data center project in Boling?

The TDLR registration identifies the project as Project Eagle.

When was Project Eagle registered?

The TDLR project registration was filed August 5, 2026.

How large will the Project Eagle data center be?

The registration lists the project at 189,060 square feet.

What is the estimated cost of the Boling data center?

The TDLR registration lists an estimated project cost of $300 million.

Has construction started at 230 Eaglewood?

The available record shows a new-construction project registration, but does not state whether construction has started.