TABS2026006736New ConstructionReview CompletePublic funds
Sl 8 - Nb Frontage Rd (csj: 3256-01-122)
From: Briar Hill Dr. To: Briar Forest Dr, Houston TX 77042
Sl 8 - Nb Frontage Rd (csj: 3256-01-122) is a publicly funded new construction project at From: Briar Hill Dr. To: Briar Forest Dr in Houston, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on November 25, 2025 as TABS2026006736. The filing lists 27,183 square feet and an estimated cost of $3.3M. Work is scheduled to start March 1, 2026 and to finish January 15, 2027. Current status: Review Complete.
- Estimated cost
- $3.3M
- Square feet
- 27,183
- Start
- Mar 1, 2026
- Completion
- Jan 15, 2027
Scope of work
Reconstruction of sidewalk, riprap, retaining walls, including erosion and drainage repairs.
Project details
TABS project numberTABS2026006736
FacilityCsj: 3256-01-122
LocationFrom: Briar Hill Dr. To: Briar Forest Dr., Houston, TX 77042
CountyHarris County
Type of workNew Construction
FundingThis project involves public funds, public land, or is a Federally funded roadway project.
Tenant fundedNo
RegisteredNovember 25, 2025
StatusReview Complete
OwnerTxdot District: Houston
Tenant Pro
Design firm & contacts Pro
Other TDLR projects in 77042
- US Anesthesia PartnersTABS2027005628 · Nov 11, 2026 · $500K
- Alief Clodine Intersections And Sidewalk ImprovementsTABS2027004088 · Oct 21, 2026 · $1.5M
- Meriton Tas HoustonTABS2027003984 · Oct 20, 2026 · $8.6M
- Thermal Engineering International - ExpansionTABS2027003879 · Oct 19, 2026 · $100K
- Level 11 Lobby, Corridor And Restroom RemodelTABS2027003750 · Oct 16, 2026 · $400K
- Hilton Houston Westchase GuestroomsTABS2027003415 · Oct 13, 2026 · $17M
- Tirz 9 - S Post Oak Sidewalk MaintenanceTABS2027002676 · Oct 2, 2026 · $400K
- Pelican Energy Partners - Lease Expansion / RenovationTABS2027001979 · Sep 25, 2026 · $800K