TABS2023014770Renovation/AlterationReview CompletePrivate
Mainfreight High Pile Storage Installation
17801 Interstate 35w Service Road, Northlake TX 76262
Mainfreight High Pile Storage Installation is a privately funded renovation / alteration project at 17801 Interstate 35w Service Road in Northlake, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on March 23, 2023 as TABS2023014770. The filing lists 68,422 square feet and an estimated cost of $800K. Work is scheduled to start May 22, 2023 and to finish June 30, 2023. Current status: Review Complete.
- Estimated cost
- $800K
- Square feet
- 68,422
- Start
- May 22, 2023
- Completion
- Jun 30, 2023
Scope of work
HPS installation
Project details
TABS project numberTABS2023014770
FacilityMainfreight
Location17801 Interstate 35W Service Road, Northlake, TX 76262
CountyDenton County
Type of workRenovation/Alteration
FundingThis project is privately funded, on private land for private use.
Tenant fundedNo
RegisteredMarch 23, 2023
StatusReview Complete
Owner Pro
Tenant Pro
Design firm & contacts Pro
Other TDLR projects in 76262
- Maa - Cooper Ridge Clubhouse & Parking RenovationTABS2027005881 · Nov 15, 2026 · $200K
- Howard Law GroupTABS2027005798 · Nov 13, 2026 · $100K
- Vfw Post 5074TABS2027005760 · Nov 13, 2026 · $500K
- Mcknight TitleTABS2027005792 · Nov 13, 2026 · $100K
- 25096 - Box Roanoke IndustrialTABS2027004757 · Oct 29, 2026 · $16M
- Lactation Room RemodelTABS2027003917 · Oct 19, 2026 · $150K
- Dal130 - Auxiliary Water BuildingTABS2027002674 · Oct 2, 2026 · $45M
- Dal130 - Data CenterTABS2027002672 · Oct 2, 2026 · $83M