TABS2024000218New ConstructionProject ClosedPrivate
Mud 119 Harmony Pathway Improvements Ph 3
Everly Bend Dr And Allegro Bend Blvd, Spring TX 77386
Mud 119 Harmony Pathway Improvements Ph 3 is a privately funded new construction project at Everly Bend Dr And Allegro Bend Blvd in Spring, Texas, registered with the Texas Department of Licensing and Regulation (TDLR) on September 5, 2023 as TABS2024000218. The filing lists 50,041 square feet and an estimated cost of $75K. Work is scheduled to start May 1, 2023 and to finish September 30, 2023. Current status: Project Closed.
- Estimated cost
- $75K
- Square feet
- 50,041
- Start
- May 1, 2023
- Completion
- Sep 30, 2023
Scope of work
Demolition, grading, site work
Project details
TABS project numberTABS2024000218
FacilityN/A
LocationEverly Bend Dr and Allegro Bend Blvd, Spring, TX 77386
CountyMontgomery County
Type of workNew Construction
FundingThis project is privately funded, on private land for private use.
Tenant fundedNo
RegisteredSeptember 5, 2023
StatusProject Closed
OwnerMud 119
Tenant Pro
Design firm & contacts Pro
Other TDLR projects in 77386
- Take 5 Oil Change - Spring (birnham Woods)TABS2027005119 · Nov 4, 2026 · $850K
- Woodson's Reserve East Section 38 & 40TABS2027005086 · Nov 3, 2026 · $750K
- Pnc TX Spring Birnham Woods GuTABS2027004018 · Oct 20, 2026 · $1.5M
- Woodson's Reserve East Section 35 And ParkTABS2027003945 · Oct 19, 2026 · $700K
- Mavis Tire - 2301 Rayford Rd, Spring, TX 77386TABS2027003711 · Oct 15, 2026 · $1.2M
- Rycon ExpansionTABS2027002988 · Oct 7, 2026 · $1.0M
- Sprouts Farmers Market- East Spring/Grand ImperialTABS2027002641 · Oct 2, 2026 · $4.2M
- Oak Ridge North Remodel - Existing Building 2TABS2027001345 · Sep 17, 2026 · $701K