groundranger
Recent · latest filing Nov 2025Commercial

600 Barnwell Lane

Aledo, TX 76008 · City Of Aledo

Aledo wastewater plant administration building addition

A 1,368-square-foot addition to the existing administration building at the Aledo Wastewater Treatment Plant is listed in a TDLR project registration dated November 5, 2025. The addition is planned to include office space, a laboratory, a restroom, a break room, a SCADA room and storage; the applicant’s estimated project cost is $528,000.

Summarized from Texas Department of Licensing and Regulation records · updated Nov 5, 2025

Projects
1
1 filings
Latest filing
Nov 5, 2025
since Nov 5, 2025
Largest scope
2,406 sf
Estimated cost
$528K
state registration

Where this project stands

Under construction

Aledo Wastewater Treatment Plant 1.2 MGD Expansion

2,406 sq ft · $528K est.

  1. RegisteredNov 5, 2025
  2. Plan review
  3. ConstructionMar '26 – Jun '28
  4. Inspected
  5. Closed
30% through of a 28-month buildMar 9, 2026 → Jun 23, 2028

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Construction of a 1,368-square-foot addition to an existing building, for a total overall building size of 2,406 square feet. the new addition will include office space, a laboratory, restroom, break room, scada room, and storage area. — administration building

    TDLR project registrationRenovation/AlterationReview Complete2,406 sq ft$528K est.
    Tenant / owner
    Aledo Wastewater Treatment Plant 1.2 Mgd Expansion
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 600 Barnwell Lane

What is being built at 600 Barnwell Lane in Aledo?

A TDLR registration describes a 1,368-square-foot addition to the Aledo Wastewater Treatment Plant’s existing administration building. It is planned to include offices, a laboratory, a restroom, a break room, a SCADA room and storage.

When was the Aledo wastewater plant project registered?

The TDLR project registration is dated November 5, 2025. Its project number is TABS2026005138.

Is this a new wastewater treatment plant?

The registration describes an addition to an existing administration building at the wastewater treatment plant, not construction of a new plant.

How large will the Aledo wastewater plant administration building be?

The registration lists the addition as 1,368 square feet and the total building size as 2,406 square feet.

How much will the Aledo wastewater plant addition cost?

The applicant’s estimated project cost is $528,000, according to the TDLR registration.