groundranger
Historic · latest filing Jan 2025Commercial

7508 Ross Rd

Austin, TX 78617

Agave East Apartments site plan approved in Austin

An apartment project called Agave East Apartments is planned at 7508 Ross Road in Austin. The City of Austin marked its site plan approved and released on January 10, 2025. A commercial sprinkler installation permit for the jobsite was filed October 16, 2024, and is listed as final.

Summarized from City of Austin records · updated Jan 10, 2025

Projects
17
17 filings
Latest filing
Jan 10, 2025
since Apr 6, 2020
Largest scope
—
Listed value
—

Where this project stands

Finaled

Sprinkler system installation - commercial jobsite ref: 2022-173000 w

  1. AppliedOct 16, 2024
  2. IssuedOct 16, 2024
  3. WorkOct '24 – Apr '25
  4. Final inspectionApr 3, 2025

Passed final inspection Apr 3, 2025.

Permit & project history

17 projects
  1. Agave East Apartments

    Agave east apartments

    City of Austin casesite_planApproved and Released
    Record
    12480620
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. Sprinkler system installation - commercial jobsite ref: 2022-173000 w

    Sprinkler system installation - commercial jobsite ref: 2022-173000 w

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. Access control permit for clubhouse

    Access control permit for clubhouse

    City of Austin permitBuilding PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  4. Underground utilities / fireline sp-2020-0237c

    Underground utilities / fireline sp-2020-0237c

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  5. Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 6101-6112 6201-6212 6301-6312

    Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 6101-6112 6201-6212 6301-6312

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  6. Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 2101-2112 2201-2212 2301-2312

    Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 2101-2112 2201-2212 2301-2312

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  7. Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 5101-5112 5201-5212 5301-5312

    Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 5101-5112 5201-5212 5301-5312

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  8. Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 4101-4112 4201-4212 4301-4312

    Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 4101-4112 4201-4212 4301-4312

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  9. Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 1101-1108 1201-12081301-1308

    Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 1101-1108 1201-12081301-1308

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  10. Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 7101-7112 7201-7212 7301-7312

    Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 7101-7112 7201-7212 7301-7312

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  11. Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 3101-3112 3201-3212 3301-3312

    Connect cellular controllers to existing domestic water heaters for austin energy to allow the utility to turn off appliances during peak demand on the power grid. demand response (dm) pilot funded by the department of energy. unit 3101-3112 3201-3212 3301-3312

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  12. New construction of an inground swimming pool

    New construction of an inground swimming pool

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  13. New construction of an inground swimming pool

    New construction of an inground swimming pool

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  14. New construction of an inground swimming pool

    New construction of an inground swimming pool

    City of Austin permitBuilding PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  15. Building pool2

    Building pool2

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  16. Moore's Crossing H/K

    Moore's crossing h/k

    City of Austin casesubdivisionExpired
    Record
    12456756
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  17. Moore's Crossing H/K

    Moore's crossing h/k

    City of Austin casesubdivisionExpired
    Record
    12421183
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Austin

Questions about 7508 Ross Rd

What is being built at 7508 Ross Road in Austin?

City of Austin records list an apartment project named Agave East Apartments at the address. Its site plan was approved and released on January 10, 2025.

When was the Agave East Apartments site plan approved?

The City of Austin case record, number 12480620, shows the site plan approved and released on January 10, 2025.

Is Agave East Apartments under construction?

The records provided show an approved and released site plan, but do not confirm construction status.

Was a sprinkler permit filed for 7508 Ross Road?

Yes. City of Austin permit 2024-139558 PP, for commercial sprinkler system installation, was filed October 16, 2024, and is listed as final.

What is the status of the Agave East Apartments project?

The City of Austin site plan case is marked approved and released. The records provided do not give a construction schedule or project cost.

Also being built nearby

All of 78617

More apartments & multifamily in 78617, pools in 78617.

Email me when a new permit is filed