Where this project stands
FinaledHb 2334 - non licensed plumbing service line - install water and wastewater yard line piping only up to 5 feet from building sp-2022-1025c
- AppliedJan 14, 2026
- IssuedOct 22, 2026
- WorkOct '26 – Oct '26
- Final inspectionOct 23, 2026
Passed final inspection Oct 23, 2026.
Permit & project history
31 projectsHb 2334 - non licensed plumbing service line - install water and wastewater yard line piping only up to 5 feet from building sp-2022-1025c
Hb 2334 - non licensed plumbing service line - install water and wastewater yard line piping only up to 5 feet from building sp-2022-1025c
City of Austin permitPlumbing PermitFinal- Record
- 2026-004785 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expansion of wastewater treatment facility admin. building. sp-2022-1025c
Expansion of wastewater treatment facility admin. building. sp-2022-1025c
City of Austin permitMechanical PermitFinal- Record
- 2024-018658 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expansion of wastewater treatment facility substation 1
Expansion of wastewater treatment facility substation 1
City of Austin permitMechanical PermitFinal- Record
- 2023-154590 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expansion of wastewater treatment facility admin. building. sp-2022-1025c
Expansion of wastewater treatment facility admin. building. sp-2022-1025c
City of Austin permitElectrical PermitActive- Record
- 2024-018622 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expansion of wastewater treatment facility admin. building. sp-2022-1025c
Expansion of wastewater treatment facility admin. building. sp-2022-1025c
City of Austin permitPlumbing PermitActive- Record
- 2024-018673 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expansion of wastewater treatment facility admin. building. sp-2022-1025c
Expansion of wastewater treatment facility admin. building. sp-2022-1025c
City of Austin permitBuilding PermitActive- Record
- 2024-018506 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expansion of wastewater treatment facility substation 1
Expansion of wastewater treatment facility substation 1
City of Austin permitElectrical PermitActive- Record
- 2023-154590 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expansion of wastewater treatment facility substation 1
Expansion of wastewater treatment facility substation 1
City of Austin permitBuilding PermitActive- Record
- 2023-154590 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 10501 Blue Bluff Rd
What is being built at 10501 Blue Bluff Road?
City records list subdivision cases for Saddle Ridge at Wildhorse Ranch and a Parmer Shopping Center at Wildhorse Ranch. They do not specify individual tenants or building details.
What are the latest development records for this address?
On October 27, 2026, the city recorded Saddle Ridge at Wildhorse Ranch and Saddle Ridge at Wildhorse Ranch Section 2 as subdivisions, under case IDs 12782159 and 13216002.
Is a Parmer Shopping Center planned at Wildhorse Ranch?
City records include Parmer Shopping Center at Wildhorse Ranch subdivision cases. Section 1 was recorded on April 28, 2026, while a Phase 1 case was listed as awaiting recordation on July 31, 2026.
Are there permits for a wastewater treatment facility here?
Yes. City records show the Northeast Interim Wastewater Treatment Plant site plan was approved and released on February 27, 2026, under case 12656684. A mechanical permit for an expansion of the facility's administrative building was finalized on November 5, 2025.
What work did the October 2026 plumbing permit cover?
Permit 2026-004785 PP was finalized on October 22, 2026. Its description covers water and wastewater yard-line piping up to five feet from the building.