908 Nueces St
Austin, TX 78701
908 Nueces Condominiums site plan approved in 2015
Austin records identify a condominium project at 908 Nueces St: its subdivision was recorded June 25, 2015, and its site plan was approved and released August 21, 2015. The latest listed permit, dated May 16, 2024, is for installing a tankless water heater and is marked final.
Summarized from City of Austin records · updated May 16, 2024
- Projects
- 3
- 3 filings
- Latest filing
- May 16, 2024
- since Jun 25, 2015
- Largest scope
- —
- Listed value
- —
Where this project stands
FinaledInstalled tankless water heater
- AppliedMay 8, 2024
- IssuedMay 16, 2024
- WorkMay '24 – Jun '24
- Final inspectionJul 13, 2026
Passed final inspection Jul 13, 2026.
1 contact on this project · 1 phone number
Permit & project history
3 projectsInstalled tankless water heater
Installed tankless water heater
City of Austin permitPlumbing PermitFinal- Record
- 2024-058204 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 908 Nueces St
What is at 908 Nueces St in Austin?
Austin records identify a project named 908 Nueces Condominiums. Its site plan was approved and released in August 2015.
Is anything currently being built at 908 Nueces?
The records provided do not show a current construction project. The latest filing is a May 16, 2024 plumbing permit for a tankless water heater, marked final.
What was the latest permit for 908 Nueces?
Permit 2024-058204 PP, filed May 16, 2024, was for installing a tankless water heater. Its status is final.
When was the 908 Nueces condominium site plan approved?
Austin case 11213233 for 908 Nueces Condominiums was approved and released on August 21, 2015.
What's happening near Travis County Facilities Management at 500 W. 10th Street?
At nearby 908 Nueces St, Austin records identify a condominium project with a site plan approved and released in 2015. The latest listed permit there is for a tankless water heater.
What is happening near Austin Independent School District on Rio Grande Street?
The nearby address 908 Nueces St has records for 908 Nueces Condominiums, including a site plan approved and released in 2015. A 2024 permit at the address covers a tankless water heater.
Also being built nearby
All of 78701- 507 W 10th StJul 1, 2025Total demolition of law office in single-family residence · 42 m away
- 600 W 10th StMay 7, 2025Replacement of complete existing central heat and air system with or without duct work like for like: 2.5 ton vertical gas system · 66 m away
- 1003 Rio Grande StAug 19, 2025Install 4 ton horizontal crossover heat pump system install 4 ton horizontal crossover heat pump system **two system demolition/install · 87 m away
- 908 San Antonio StSep 16, 2025Installing tpo (overlay) on the current parking garage stairwell roof structure · 95 m away
- 603 W 9th StJul 17, 2026Replacement of complete existing central heat and air system with or without duct work · 109 m away
- 910 San Antonio StMar 2, 2007Travis county parking garage expansion & repair · 113 m away
- 500 W 10th StMar 3, 2026Eplan: commercial expedited review - remodel to existing jail reception area · 117 m away
- 809 Rio Grande StMay 23, 2024Single-layer roof replacement 22 sq total of asphalt dimensional shingles and 6 squares of modified bitumen roofing. no roof or attic penetrations · 117 m away
- 509 W 11th StJul 10, 2025Replacement or addition to an existing unit of up to four supply or return duct runs three air handler replacements (ahu# 9 10 & 11). the units are like for like trane units. only the units will be replaced all existing duct and hydronic piping will remain in place. * not related to the active 2025-060975 pr the area being worked on is a penthouse area of the building which seems to be completely separated from the other work · 118 m away
- 902 Rio Grande StJul 20, 2026Re-roof · 124 m away
- 500 W. 10th Street · Travis County Facilities ManagementSep 20, 2024Tcj magistrate court — renovation/alteration — renovating the courtroom space to allow for holding cells, interview rooms, courtroom, restrooms and offices to include plumbing, hvac, electrical in 2789 sq ft · 126 m away
- 1000 Rio Grande StOct 8, 2024Installing a whole home standby generator with an automatic transfer switch; insatlling a dedicate gas line for a whole home standby generator. [7 day review] · 127 m away