groundranger
Historic · latest filing Oct 2024Commercial

1120 To 1900 Airport Blvd

Austin, TX 78702 · City Of Austin

Airport Boulevard path and bikeway planned from MLK to Springdale

The City of Austin registered work for a shared-use path, bikeway and sidewalk along the west side of Airport Boulevard from MLK Jr. Boulevard to Springdale Road. The TDLR project registration was filed October 17, 2024, and also describes some bus stop relocations and installations. The applicant’s estimated project cost is $4,639,132.

Summarized from Texas Department of Licensing and Regulation records · updated Oct 17, 2024

Projects
1
1 filings
Latest filing
Oct 17, 2024
since Oct 17, 2024
Largest scope
337,747 sf
Estimated cost
$4.6M
state registration

Where this project stands

Finishing up · inspection next

Airport Blvd. Section C3 MLK Jr. Blvd to Springdale Rd

337,747 sq ft · $4.6M est.

  1. RegisteredOct 17, 2024
  2. Plan review
  3. ConstructionMay '25 – Jun '26
  4. Inspectednow
  5. Closed

Scheduled to finish Jun 30, 2026; the state inspection hasn't been filed yet.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Installation of shared-use-path, bikeway, sidewalk, along west side of airport blvd; some bus stop relocation/installation. total about 337,747sf of limits of construction. — airport blvd. from mlk jr. blvd to springdale rd

    TDLR project registrationRenovation/AlterationReview Complete337,747 sq ft$4.6M est.
    Tenant / owner
    Airport Blvd. Section C3 Mlk Jr. Blvd To Springdale Rd
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 1120 To 1900 Airport Blvd

What is being built at 1120 to 1900 Airport Boulevard?

The registered project includes a shared-use path, bikeway and sidewalk along the west side of Airport Boulevard, from MLK Jr. Boulevard to Springdale Road. It also includes some bus stop relocations and installations.

When was the Airport Boulevard project permitted?

The TDLR registration, project TABS2025003484, was filed October 17, 2024. Its status is listed as Review Complete.

Is a new building going up on Airport Boulevard?

The registration describes transportation improvements, not a new building: a shared-use path, bikeway, sidewalk and bus stop work along Airport Boulevard.

What is being built near Jay Paul Company on Springdale Road?

A City of Austin project is registered for the west side of Airport Boulevard between MLK Jr. Boulevard and Springdale Road. The work includes a shared-use path, bikeway and sidewalk.

What work is planned near E1even11?

The Airport Boulevard project registration describes a shared-use path, bikeway and sidewalk along the corridor from MLK Jr. Boulevard to Springdale Road. It also notes some bus stop relocation and installation.

How much will the Airport Boulevard project cost?

The applicant’s TDLR estimate is $4,639,132 for the project. This is an estimate, not a confirmed final cost.

Also being built nearby

All of 78702
Email me when it passes inspection