2318 Morelos St
Austin, TX 78702
Residential property permitted for administrative office use
A change of use from residential to administrative office was permitted at 2318 Morelos St on April 30, 2024. The permit also allows five additional parking spaces; it says no work is being performed on the building.
Summarized from City of Austin records · updated Apr 30, 2024
- Projects
- 2
- 2 filings
- Latest filing
- Apr 30, 2024
- since Apr 30, 2024
- Largest scope
- —
- Listed value
- —
Where this project stands
FinaledChange of use from residential to administrative office. adding 5 additional parking spaces per site plan. no work being performed on building
- AppliedAug 11, 2023
- IssuedApr 30, 2024
- WorkApr '24 – Aug '24
- Final inspectionAug 23, 2024
Passed final inspection Aug 23, 2024.
2 contacts on this project · 2 phone numbers
Permit & project history
2 projectsChange of use from residential to administrative office. adding 5 additional parking spaces per site plan. no work being performed on building
Change of use from residential to administrative office. adding 5 additional parking spaces per site plan. no work being performed on building
City of Austin permitBuilding PermitFinal- Record
- 2024-039164 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Construct two new driveway approach of 101 ft on the east side of the project and 23 ft on the back. driveway approach is from the alley. sam wests waiver is attached. *rs
Construct two new driveway approach of 101 ft on the east side of the project and 23 ft on the back. driveway approach is from the alley. sam wests waiver is attached. *rs
City of Austin permitDriveway / SidewalksFinal- Record
- 2023-082498 DS
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 2318 Morelos St
What is being built at 2318 Morelos St in Austin?
A City of Austin permit indicates the property is changing from residential use to an administrative office. It also includes five additional parking spaces, with no building work proposed.
When was the office use permitted at 2318 Morelos St?
The City of Austin issued permit 2024-039164 BP on April 30, 2024. Its status is Final.
Are they building a new office at 2318 Morelos St?
The permit describes a change of use from residential to administrative office, not new building construction. It says no work is being performed on the building.
How many parking spaces are being added at 2318 Morelos St?
The April 30, 2024 permit includes five additional parking spaces.
What is being permitted near Dc-2422 at 2422 E 7th St?
At 2318 Morelos St, about 102 meters from Dc-2422, a permit allows a change from residential to administrative office use and five additional parking spaces.
Was driveway work permitted at 2318 Morelos St?
Yes. A City of Austin driveway permit dated July 21, 2023, describes two new driveway approaches: 101 feet on the east side of the project and 23 feet at the back, accessed from the alley.
Also being built nearby
All of 78702- 2316 Morelos StMar 17, 2025Change of use from automotive repair services to personal improvement services. no construction proposed-first and second floor · 17 m away
- 2314 Morelos StOct 14, 2024Installed 7 hose bibbs and shutoffs with a test gauge · 54 m away
- 2404 E 7th StDec 23, 2024Main exterior water line replacement · 62 m away
- 2409 E 7th StJun 6, 2025Retrofit interior lighting permit part of aesblp upgrading to led light bulbs. one for one. only existing lights. there are 38 led tubes and 46 led light bulbs · 67 m away
- 2312 Morelos StFeb 26, 2025Cap off with ww 11/26/2024---approved to backfill water and sewer trenches for safety--slc · 69 m away
- 2308 Morelos StAug 4, 2026Morelos street lot 3 · 82 m away
- 718 Northwestern AveMar 2, 2007Safi warehouse · 83 m away
- 2307 Coronado StSep 24, 2026Hotel coronado · 89 m away
- 2305 Coronado StMar 11, 20152305 coronado street · 92 m away
- 2321 E 7th StNov 27, 2024Replace drain yard line cash american pawn · 93 m away
- 2406 Hidalgo StJul 11, 20172406 hidalgo street · 95 m away
- 2304 Morelos StOct 29, 2026Morelos street · 97 m away