City of Austin permits filed in July and August 2025 indicate interior fit-outs in several suites at 3100 E 5th St. Work includes architectural and mechanical, electrical and plumbing improvements, plus accessibility and security upgrades and exterior egress improvements. The records do not identify tenants or a new use for the building.

Summarized from City of Austin records · updated Aug 4, 2025

Projects
21
21 filings
Latest filing
Aug 4, 2025
since Oct 22, 2024
Largest scope
—
Listed value
—

Permit & project history

21 projects
  1. Interior fit-out including architectural and mep improvements. fit-out for this phase is limited to suite100 (on 1st floor 12308sf)

    Interior fit-out including architectural and mep improvements. fit-out for this phase is limited to suite100 (on 1st floor 12308sf)

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. Suite 200(on 2nd floor 22243sf). limited tas/tdlr and security improvements on both floors. improvements include: accessibility revision to restrooms; addition of card readers & security cameras. there is a glass enclosure at existing elevators lobby from 1st floor up to existing roof; screen protection added at existing stairs. exterior improvement includes addition of ev charging station dumpster structure and addition for safety egress of compliant ramp and stair on north side of building

    Suite 200(on 2nd floor 22243sf). limited tas/tdlr and security improvements on both floors. improvements include: accessibility revision to restrooms; addition of card readers & security cameras. there is a glass enclosure at existing elevators lobby from 1st floor up to existing roof; screen protection added at existing stairs. exterior improvement includes addition of ev charging station dumpster structure and addition for safety egress of compliant ramp and stair on north side of building

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. Interior fit-out including architectural and mep improvements. suite 120 (on 1st floor 1389sf)

    Interior fit-out including architectural and mep improvements. suite 120 (on 1st floor 1389sf)

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  4. Interior fit-out including architectural and mep improvements. fit-out for this phase is limited to suite100 (on 1st floor 12308sf)

    Interior fit-out including architectural and mep improvements. fit-out for this phase is limited to suite100 (on 1st floor 12308sf)

    City of Austin permitMechanical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  5. Interior fit-out including architectural and mep improvements. suite 120 (on 1st floor 1389sf)

    Interior fit-out including architectural and mep improvements. suite 120 (on 1st floor 1389sf)

    City of Austin permitMechanical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  6. Interior fit-out including architectural and mep improvements. suite 120 (on 1st floor 1389sf)

    Interior fit-out including architectural and mep improvements. suite 120 (on 1st floor 1389sf)

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  7. Interior fit-out including architectural and mep improvements. fit-out for this phase is limited to suite100 (on 1st floor 12308sf)

    Interior fit-out including architectural and mep improvements. fit-out for this phase is limited to suite100 (on 1st floor 12308sf)

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  8. Suite 200(on 2nd floor 22243sf). limited tas/tdlr and security improvements on both floors. improvements include: accessibility revision to restrooms; addition of card readers & security cameras. there is a glass enclosure at existing elevators lobby from 1st floor up to existing roof; screen protection added at existing stairs. exterior improvement includes addition of ev charging station dumpster structure and addition for safety egress of compliant ramp and stair on north side of building

    Suite 200(on 2nd floor 22243sf). limited tas/tdlr and security improvements on both floors. improvements include: accessibility revision to restrooms; addition of card readers & security cameras. there is a glass enclosure at existing elevators lobby from 1st floor up to existing roof; screen protection added at existing stairs. exterior improvement includes addition of ev charging station dumpster structure and addition for safety egress of compliant ramp and stair on north side of building

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  9. Suite 200(on 2nd floor 22243sf). limited tas/tdlr and security improvements on both floors. improvements include: accessibility revision to restrooms; addition of card readers & security cameras. there is a glass enclosure at existing elevators lobby from 1st floor up to existing roof; screen protection added at existing stairs. exterior improvement includes addition of ev charging station dumpster structure and addition for safety egress of compliant ramp and stair on north side of building

    Suite 200(on 2nd floor 22243sf). limited tas/tdlr and security improvements on both floors. improvements include: accessibility revision to restrooms; addition of card readers & security cameras. there is a glass enclosure at existing elevators lobby from 1st floor up to existing roof; screen protection added at existing stairs. exterior improvement includes addition of ev charging station dumpster structure and addition for safety egress of compliant ramp and stair on north side of building

    City of Austin permitMechanical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  10. Interior fit-out including architectural and mep improvements of the southeast corner of first floor approx 8900 sq ft fit-out for this phase is limited to suite 180 located on the 1st floor. the main improvements include assembly and business spaces and support paces. other improvements include new exterior doors hand railing and addition of card readers and security cameras. limited tas/tdlr and security improvements also included

    Interior fit-out including architectural and mep improvements of the southeast corner of first floor approx 8900 sq ft fit-out for this phase is limited to suite 180 located on the 1st floor. the main improvements include assembly and business spaces and support paces. other improvements include new exterior doors hand railing and addition of card readers and security cameras. limited tas/tdlr and security improvements also included

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  11. Interior fit-out including architectural and mep improvements. suite 120 (on 1st floor 1389sf)

    Interior fit-out including architectural and mep improvements. suite 120 (on 1st floor 1389sf)

    City of Austin permitBuilding PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  12. Interior fit-out including architectural and mep improvements. fit-out for this phase is limited to suite100 (on 1st floor 12308sf)

    Interior fit-out including architectural and mep improvements. fit-out for this phase is limited to suite100 (on 1st floor 12308sf)

    City of Austin permitBuilding PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  13. Suite 200(on 2nd floor 22243sf). limited tas/tdlr and security improvements on both floors. improvements include: accessibility revision to restrooms; addition of card readers & security cameras. there is a glass enclosure at existing elevators lobby from 1st floor up to existing roof; screen protection added at existing stairs. exterior improvement includes addition of ev charging station dumpster structure and addition for safety egress of compliant ramp and stair on north side of building

    Suite 200(on 2nd floor 22243sf). limited tas/tdlr and security improvements on both floors. improvements include: accessibility revision to restrooms; addition of card readers & security cameras. there is a glass enclosure at existing elevators lobby from 1st floor up to existing roof; screen protection added at existing stairs. exterior improvement includes addition of ev charging station dumpster structure and addition for safety egress of compliant ramp and stair on north side of building

    City of Austin permitBuilding PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  14. Interior fit-out including architectural and mep improvements of the southeast corner of first floor approx 8900 sq ft fit-out for this phase is limited to suite 180 located on the 1st floor. the main improvements include assembly and business spaces and support paces. other improvements include new exterior doors hand railing and addition of card readers and security cameras. limited tas/tdlr and security improvements also included

    Interior fit-out including architectural and mep improvements of the southeast corner of first floor approx 8900 sq ft fit-out for this phase is limited to suite 180 located on the 1st floor. the main improvements include assembly and business spaces and support paces. other improvements include new exterior doors hand railing and addition of card readers and security cameras. limited tas/tdlr and security improvements also included

    City of Austin permitMechanical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  15. Interior fit-out including architectural and mep improvements of the southeast corner of first floor approx 8900 sq ft fit-out for this phase is limited to suite 180 located on the 1st floor. the main improvements include assembly and business spaces and support paces. other improvements include new exterior doors hand railing and addition of card readers and security cameras. limited tas/tdlr and security improvements also included

    Interior fit-out including architectural and mep improvements of the southeast corner of first floor approx 8900 sq ft fit-out for this phase is limited to suite 180 located on the 1st floor. the main improvements include assembly and business spaces and support paces. other improvements include new exterior doors hand railing and addition of card readers and security cameras. limited tas/tdlr and security improvements also included

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  16. Interior fit-out including architectural and mep improvements of the southeast corner of first floor approx 8900 sq ft fit-out for this phase is limited to suite 180 located on the 1st floor. the main improvements include assembly and business spaces and support paces. other improvements include new exterior doors hand railing and addition of card readers and security cameras. limited tas/tdlr and security improvements also included

    Interior fit-out including architectural and mep improvements of the southeast corner of first floor approx 8900 sq ft fit-out for this phase is limited to suite 180 located on the 1st floor. the main improvements include assembly and business spaces and support paces. other improvements include new exterior doors hand railing and addition of card readers and security cameras. limited tas/tdlr and security improvements also included

    City of Austin permitBuilding PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  17. Interior fit-out including architectural and mep improvements to white box space. fit-out is limited to suite 300 located on 3rd floor. suite 320 and an egress corridor are included for fire life safety purposes only. limited tas/tdlr and security improvements are also included on the first floor to support the occupancy of the 3rd floor. the first floor improvements include accessibility revisions to the restroom

    Interior fit-out including architectural and mep improvements to white box space. fit-out is limited to suite 300 located on 3rd floor. suite 320 and an egress corridor are included for fire life safety purposes only. limited tas/tdlr and security improvements are also included on the first floor to support the occupancy of the 3rd floor. the first floor improvements include accessibility revisions to the restroom

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  18. Interior fit-out including architectural and mep improvements to white box space. fit-out is limited to suite 300 located on 3rd floor. suite 320 and an egress corridor are included for fire life safety purposes only. limited tas/tdlr and security improvements are also included on the first floor to support the occupancy of the 3rd floor. the first floor improvements include accessibility revisions to the restroom

    Interior fit-out including architectural and mep improvements to white box space. fit-out is limited to suite 300 located on 3rd floor. suite 320 and an egress corridor are included for fire life safety purposes only. limited tas/tdlr and security improvements are also included on the first floor to support the occupancy of the 3rd floor. the first floor improvements include accessibility revisions to the restroom

    City of Austin permitPlumbing PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  19. Interior fit-out including architectural and mep improvements to white box space. fit-out is limited to suite 300 located on 3rd floor. suite 320 and an egress corridor are included for fire life safety purposes only. limited tas/tdlr and security improvements are also included on the first floor to support the occupancy of the 3rd floor. the first floor improvements include accessibility revisions to the restroom

    Interior fit-out including architectural and mep improvements to white box space. fit-out is limited to suite 300 located on 3rd floor. suite 320 and an egress corridor are included for fire life safety purposes only. limited tas/tdlr and security improvements are also included on the first floor to support the occupancy of the 3rd floor. the first floor improvements include accessibility revisions to the restroom

    City of Austin permitMechanical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  20. Interior fit-out including architectural and mep improvements to white box space. fit-out is limited to suite 300 located on 3rd floor. suite 320 and an egress corridor are included for fire life safety purposes only. limited tas/tdlr and security improvements are also included on the first floor to support the occupancy of the 3rd floor. the first floor improvements include accessibility revisions to the restroom

    Interior fit-out including architectural and mep improvements to white box space. fit-out is limited to suite 300 located on 3rd floor. suite 320 and an egress corridor are included for fire life safety purposes only. limited tas/tdlr and security improvements are also included on the first floor to support the occupancy of the 3rd floor. the first floor improvements include accessibility revisions to the restroom

    City of Austin permitBuilding PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  21. Replace burned 800 amp 480 volt non fusible disconnect

    Replace burned 800 amp 480 volt non fusible disconnect

    City of Austin permitElectrical PermitExpired
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Austin

Questions about 3100 E 5th St

What is being built at 3100 E 5th St in Austin?

City permits indicate interior fit-outs in suites 100, 120, 180 and 200, along with accessibility, security and exterior improvements. The records describe work to an existing building, not a new building.

What work is happening in Suite 100 at 3100 E 5th St?

Permits filed July 31 and August 1 and 4, 2025, cover an interior fit-out with architectural, mechanical, electrical and plumbing improvements. The described area is 12,308 square feet.

What improvements are planned for Suite 200?

Permits filed August 1 and 4, 2025, describe work in the 22,243-square-foot second-floor suite, including restroom accessibility revisions, card readers and security cameras. The plans also list an elevator-lobby glass enclosure, stair screening, an EV charging station, a dumpster structure, and a compliant ramp and stair for safe egress.

What is being changed in Suite 180 at 3100 E 5th St?

A permit filed August 1, 2025, describes an approximately 8,900-square-foot first-floor fit-out for assembly and business spaces and support areas. Listed improvements include exterior doors, hand railing, card readers and security cameras.

Is a new business opening at 3100 E 5th St?

The available City of Austin permits describe suite fit-outs and building upgrades but do not name a tenant or identify a new business.

What work is happening near Gallo East on Tillery Street?

At 3100 E 5th St, about 220 meters from Gallo East at 405 Tillery Street, City of Austin permits filed in July and August 2025 indicate interior suite fit-outs and accessibility, security and exterior upgrades.