1601 Westover Rd
Austin, TX 78703
Sewer and gas line repairs permitted at 1601 Westover Road
City of Austin permits indicate plumbing repairs at 1601 Westover Road, not a new building project. A March 5, 2025, permit covers a gas line repair; a February 9, 2026, permit covers replacement of the guest house sewer ejector station and discharge line.
Summarized from City of Austin records · updated Feb 9, 2026
- Projects
- 2
- 2 filings
- Latest filing
- Feb 9, 2026
- since Mar 5, 2025
- Largest scope
- —
- Listed value
- —
Where this project stands
FinaledReplace sewer ejector station and discharge line for guest house in the back approximately 90 feet of 2 inch forced drain discharge line and replace with schedule forty pvc
- AppliedFeb 6, 2026
- IssuedFeb 9, 2026
- WorkFeb '26 – Feb '26
- Final inspectionJul 13, 2026
Passed final inspection Jul 13, 2026.
1 contact on this project · 1 phone number
Permit & project history
2 projectsReplace sewer ejector station and discharge line for guest house in the back approximately 90 feet of 2 inch forced drain discharge line and replace with schedule forty pvc
Replace sewer ejector station and discharge line for guest house in the back approximately 90 feet of 2 inch forced drain discharge line and replace with schedule forty pvc
City of Austin permitPlumbing PermitFinal- Record
- 2026-014771 PP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Repair to gas line
Repair to gas line
City of Austin permitPlumbing PermitFinal- Record
- 2025-023923 PP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 1601 Westover Rd
What is happening at 1601 Westover Road?
City of Austin permits cover a gas line repair and replacement of a sewer ejector station and discharge line for the guest house. Both permits are marked final.
Is a new building being constructed at 1601 Westover Road?
The available permits describe plumbing repairs, not new construction. They cover a gas line and the guest house sewer ejector station and discharge line.
What work does permit 2026-014771 PP cover?
The February 9, 2026, permit covers replacing the guest house sewer ejector station and about 90 feet of 2-inch forced drain discharge line with Schedule 40 PVC.
When was the sewer work at 1601 Westover Road permitted?
The City of Austin issued permit 2026-014771 PP on February 9, 2026. Its status is final.
Was a gas line repair permitted at 1601 Westover Road?
Yes. City of Austin permit 2025-023923 PP, dated March 5, 2025, covers a gas line repair and is marked final.
Also being built nearby
All of 78703- 1600 Preston AveMar 19, 2025Replacement of complete existing central heat and air system with or without duct work · 50 m away
- 1518 Preston AveDec 4, 2024Gas test · 55 m away
- 1514 Westover RdSep 24, 2026Building. 1: addition and remodel - remodel of existing primary single family residence including a patio extension and addition to the rear of the home · 71 m away
- 1609 Westover RdJan 21, 2026Construct new driveway approach of 11 ft and walkway of 5.1 lf · 72 m away
- 1514 Preston AveMay 30, 2025Replacement of complete existing central heat and air system with or without duct work like for like: 4 ton gas system · 81 m away
- 1608 Westover RdNov 21, 2025Replacement of an existing water heater tankless · 82 m away
- 1509 Westover RdJul 17, 2024Replacement of complete existing central heat and air system with or without duct work · 96 m away
- 1510 Westover RdOct 30, 2025Generator gas line ran along the side of home · 98 m away
- 1515 Preston AveAug 10, 2026Replacement of complete existing central heat and air system with or without duct work · 103 m away
- 1605 Northwood RdMay 13, 2026Express: foundation repair · 105 m away
- 1610 Preston AveAug 7, 2025Gas work for home standby generator · 106 m away
- 1517 Northwood RdMar 19, 2026Run 90 of 1.25 poly to generator · 110 m away