1124 S. Interstate Hwy
Austin, TX 78704 · Housing Authority Of Coa
AHA HQ renovation planned for all three floors
A renovation is planned for the existing three-story building at 1124 S. Interstate Hwy in Austin. The project was registered with TDLR on June 30, 2026, and calls for new walls, doors, ceilings, millwork, finishes and mechanical, electrical and plumbing work across all three levels. The applicant’s estimated project cost is $8 million.
Summarized from Texas Department of Licensing and Regulation records · updated Jun 30, 2026
- Projects
- 1
- 1 filings
- Latest filing
- Jun 30, 2026
- since Jun 30, 2026
- Largest scope
- 47,831 sf
- Estimated cost
- $8.0M
- state registration
Where this project stands
Under constructionAHA HQ Renovation - Phase 2
47,831 sq ft · $8.0M est.
- RegisteredJun 30, 2026
- Plan review
- ConstructionAug '26 – Dec '26
- Inspected
- Closed
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectRenovation of an existing 3-story building to include new walls, door/frames/hardware, ceilings, millwork, finishes, and mep items. scope of work to occur on all three levels. — housing authority of coa
TDLR project registrationRenovation/AlterationReview Complete47,831 sq ft$8.0M est.- Project #
- TABS2026024154
- Tenant / owner
- Aha Hq Renovation - Phase 2
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 1124 S. Interstate Hwy
What is being built at 1124 S. Interstate Hwy in Austin?
The project is a renovation of an existing three-story building, not a new building. The registered scope includes work across all three levels.
What is the AHA HQ renovation project in Austin?
The TDLR registration names it “AHA HQ Renovation - Phase 2.” The scope includes new walls, doors and frames, ceilings, millwork, finishes, and mechanical, electrical and plumbing work.
When was the AHA HQ renovation registered?
The project was registered with TDLR on June 30, 2026. Its registration number is TABS2026024154.
How much will the renovation at 1124 S. Interstate Hwy cost?
The applicant’s estimated cost for the project is $8 million. This is an estimate, not a confirmed final cost.
How large is the 1124 S. Interstate Hwy renovation?
The TDLR registration lists the project at 47,831 square feet and says work will occur on all three floors.
What work is included in the AHA HQ Renovation - Phase 2?
The registered scope lists new walls, door and frame hardware, ceilings, millwork and finishes, along with mechanical, electrical and plumbing items.