groundranger
Active · latest filing Nov 2026Residential

3011 Fontana Dr

Austin, TX 78704

Two-story duplex permitted at 3011 Fontana Drive

City of Austin building permits filed September 12, 2025, indicate a new two-story duplex at 3011 Fontana Dr, with two units, each described as having three bedrooms and 2.5 bathrooms. Later permits cover mechanical, electrical and plumbing work, and a November 5, 2026, permit covers a driveway approach, sidewalk and curb and gutter.

Summarized from City of Austin records · updated Nov 5, 2026

Projects
12
12 filings
Latest filing
Nov 5, 2026
since Jun 26, 2024
Largest scope
—
Listed value
—

Where this project stands

Permit active · work underway

Construct new driveway approach of 12 ft and sidewalk of 44 lf and curb/gutter of 10ft. walkway from back of curb to property

  1. AppliedMay 22, 2025
  2. IssuedNov 5, 2026
  3. WorkNov '26 – Apr '27
  4. Final inspection
8% through of the permit windowNov 5, 2026 → Apr 26, 2027

1 contact on this project · 1 phone number

Permit & project history

12 projects
  1. Construct new driveway approach of 12 ft and sidewalk of 44 lf and curb/gutter of 10ft. walkway from back of curb to property

    Construct new driveway approach of 12 ft and sidewalk of 44 lf and curb/gutter of 10ft. walkway from back of curb to property

    City of Austin permitDriveway / SidewalksActive
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. New construction of a 2-story duplex (unit b) with 3 bedrooms 2.5 bathrooms per unit

    New construction of a 2-story duplex (unit b) with 3 bedrooms 2.5 bathrooms per unit

    City of Austin permitMechanical PermitActive
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. New construction of a 2-story duplex (unit a) with 3 bedrooms 2.5 bathrooms per unit

    New construction of a 2-story duplex (unit a) with 3 bedrooms 2.5 bathrooms per unit

    City of Austin permitMechanical PermitActive
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  4. Reference: 2025-115675ep & 2025-115676 temp. overhead meter loop for construction will be building new duplex

    Reference: 2025-115675ep & 2025-115676 temp. overhead meter loop for construction will be building new duplex

    City of Austin permitElectrical PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  5. New construction of a 2-story duplex (unit a) with 3 bedrooms 2.5 bathrooms per unit

    New construction of a 2-story duplex (unit a) with 3 bedrooms 2.5 bathrooms per unit

    City of Austin permitElectrical PermitActive
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  6. New construction of a 2-story duplex (unit b) with 3 bedrooms 2.5 bathrooms per unit

    New construction of a 2-story duplex (unit b) with 3 bedrooms 2.5 bathrooms per unit

    City of Austin permitElectrical PermitActive
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  7. New construction of a 2-story duplex (unit b) with 3 bedrooms 2.5 bathrooms per unit

    New construction of a 2-story duplex (unit b) with 3 bedrooms 2.5 bathrooms per unit

    City of Austin permitPlumbing PermitActive
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  8. New construction of a 2-story duplex (unit a) with 3 bedrooms 2.5 bathrooms per unit

    New construction of a 2-story duplex (unit a) with 3 bedrooms 2.5 bathrooms per unit

    City of Austin permitPlumbing PermitActive
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  9. New construction of a 2-story duplex (unit a) with 3 bedrooms 2.5 bathrooms per unit

    New construction of a 2-story duplex (unit a) with 3 bedrooms 2.5 bathrooms per unit

    City of Austin permitBuilding PermitActive
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  10. New construction of a 2-story duplex (unit b) with 3 bedrooms 2.5 bathrooms per unit

    New construction of a 2-story duplex (unit b) with 3 bedrooms 2.5 bathrooms per unit

    City of Austin permitBuilding PermitActive
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  11. Cap off water and waste water

    Cap off water and waste water

    City of Austin permitPlumbing PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  12. Total demolition of sfr 1025sqft circa 1956 ***the building shall not be demolished until after the contractor has fulfilled the neighbor notification requirements outlined in steps 5 & 6 of the demolition webpage

    Total demolition of sfr 1025sqft circa 1956 ***the building shall not be demolished until after the contractor has fulfilled the neighbor notification requirements outlined in steps 5 & 6 of the demolition webpage

    City of Austin permitBuilding PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Austin

Questions about 3011 Fontana Dr

What is being built at 3011 Fontana Dr in Austin?

City of Austin permits indicate a new two-story duplex with units A and B. Each unit is described as having three bedrooms and 2.5 bathrooms.

How many units are planned at 3011 Fontana Dr?

The permit records describe a duplex with two units, labeled A and B. Building permits 2025-115675 BP and 2025-115676 BP were filed September 12, 2025.

When was the duplex at 3011 Fontana Dr permitted?

The building permits for units A and B were filed September 12, 2025. The records also show later trade permits for plumbing, electrical and mechanical work.

How many bedrooms and bathrooms will each unit have at 3011 Fontana Dr?

The permits describe each unit as having three bedrooms and 2.5 bathrooms.

Are there permits for site work at 3011 Fontana Dr?

Yes. A City of Austin permit filed November 5, 2026, covers a 12-foot driveway approach, 44 linear feet of sidewalk and 10 feet of curb and gutter.

Is the duplex at 3011 Fontana Dr complete?

The records include active building and trade permits, as well as a final temporary electrical permit. They do not establish that the duplex is complete.

Also being built nearby

All of 78704

More demolitions in 78704, townhomes in 78704.

Email me when it passes final inspection