721 Barton Springs Rd
Austin, TX 78704
Office renovations and equipment upgrades at 721 Barton Springs
City of Austin permits indicate interior renovations to administrative office space at 721 Barton Springs Road, including minor exterior work for ADA egress; the related permits were filed March 31 and April 2, 2025. Later permits cover fire-system work and replacement of equipment serving the existing office building, with the latest filing dated March 25, 2026.
Summarized from City of Austin records · updated Mar 25, 2026
- Projects
- 11
- 11 filings
- Latest filing
- Mar 25, 2026
- since Jan 3, 2025
- Largest scope
- —
- Listed value
- —
Where this project stands
FinaledReplace an existing diesel option generator automatic transfer switch docking station and install stairs/platform on new concrete apron on existing equipment pad. site plan exemption not required less than 100 sq ft for existing office building-separate scope of work than pr 2025-007895
- AppliedAug 27, 2025
- IssuedMar 25, 2026
- WorkMar '26 – Apr '26
- Final inspectionApr 8, 2026
Passed final inspection Apr 8, 2026.
1 contact on this project · 1 phone number
Permit & project history
11 projectsReplace an existing diesel option generator automatic transfer switch docking station and install stairs/platform on new concrete apron on existing equipment pad. site plan exemption not required less than 100 sq ft for existing office building-separate scope of work than pr 2025-007895
Replace an existing diesel option generator automatic transfer switch docking station and install stairs/platform on new concrete apron on existing equipment pad. site plan exemption not required less than 100 sq ft for existing office building-separate scope of work than pr 2025-007895
City of Austin permitMechanical PermitFinal- Record
- 2025-144816 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Replace an existing diesel option generator automatic transfer switch docking station and install stairs/platform on new concrete apron on existing equipment pad. site plan exemption not required less than 100 sq ft for existing office building-separate scope of work than pr 2025-007895
Replace an existing diesel option generator automatic transfer switch docking station and install stairs/platform on new concrete apron on existing equipment pad. site plan exemption not required less than 100 sq ft for existing office building-separate scope of work than pr 2025-007895
City of Austin permitElectrical PermitFinal- Record
- 2025-144816 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Replace an existing diesel option generator automatic transfer switch docking station and install stairs/platform on new concrete apron on existing equipment pad. site plan exemption not required less than 100 sq ft for existing office building-separate scope of work than pr 2025-007895
Replace an existing diesel option generator automatic transfer switch docking station and install stairs/platform on new concrete apron on existing equipment pad. site plan exemption not required less than 100 sq ft for existing office building-separate scope of work than pr 2025-007895
City of Austin permitBuilding PermitFinal- Record
- 2025-144816 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Add new piv to existing fire underground lead in
Add new piv to existing fire underground lead in
City of Austin permitPlumbing PermitFinal- Record
- 2025-144662 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Replacement of mini-split system
Replacement of mini-split system
City of Austin permitMechanical PermitFinal- Record
- 2025-029961 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Interior renovation of administrative office space with minor exterior civil work for ada egress. pupr2
Interior renovation of administrative office space with minor exterior civil work for ada egress. pupr2
City of Austin permitPlumbing PermitFinal- Record
- 2025-034467 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Interior renovation of administrative office space with minor exterior civil work for ada egress. pupr2
Interior renovation of administrative office space with minor exterior civil work for ada egress. pupr2
City of Austin permitElectrical PermitFinal- Record
- 2025-034467 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Interior renovation of administrative office space with minor exterior civil work for ada egress. pupr2
Interior renovation of administrative office space with minor exterior civil work for ada egress. pupr2
City of Austin permitBuilding PermitFinal- Record
- 2025-034467 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Interior renovation of administrative office space with minor exterior civil work for ada egress. pupr2
Interior renovation of administrative office space with minor exterior civil work for ada egress. pupr2
City of Austin permitMechanical PermitFinal- Record
- 2025-034467 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Replacement of mini-split system replace mini split system with like-for-like unit at town lake center
Replacement of mini-split system replace mini split system with like-for-like unit at town lake center
City of Austin permitMechanical PermitFinal- Record
- 2024-167364 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Emergency structural repairs existing parking garage structure
Emergency structural repairs existing parking garage structure
City of Austin permitBuilding PermitFinal- Record
- 2023-137233 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 721 Barton Springs Rd
What is being built at 721 Barton Springs Road?
Permits indicate renovations and equipment updates at an existing office building, not a new building. The 2025 work included an interior administrative-office renovation and minor exterior work for ADA egress.
When were permits filed for work at 721 Barton Springs?
The earliest listed filing is a mechanical permit dated May 12, 2025. The latest is permit 2025-144816 MP, filed March 25, 2026, for generator-related work.
What renovations are planned for the office at 721 Barton Springs?
Permits 2025-034467 BP, EP and MP, dated March 31, 2025, and plumbing permit 2025-034467 PP, dated April 2, describe an interior renovation of administrative office space and minor exterior civil work for ADA egress.
Is the work at 721 Barton Springs a new office building?
The permit descriptions refer to an existing office building and renovations or equipment replacements. The records provided do not describe construction of a new building.
What generator work is permitted at 721 Barton Springs?
Permits describe replacing an existing diesel generator automatic transfer switch docking station and installing stairs and a platform on a new concrete apron over the existing equipment pad. The related building permit, 2025-144816 BP, is dated November 12, 2025.
What is being worked on near 801 Barton Springs?
At 721 Barton Springs, City permits describe office renovations and equipment updates. The records list the address as about 58 meters from 801 Barton Springs.
Also being built nearby
All of 78704- 721 Barton Springs Road · City Of AustinDec 28, 2024Town lake center renovation — renovation/alteration — renovation of 5 floor building for office space totaling 105,993 usf. first floor space includes employee break room, fitness facilities, public conferencing, boards & commissions room, and training room. mechanical, electrical, plumbing, etc · 51 m away
- 801 Barton Springs RdSep 8, 2026Office suite on level 7. renovating existing work-sharing layout to become spec suite office space with conference room offices phone rooms and support spaces. no no access control in scope. existing lighting to be relocated/reused. remainder of units submitted as separate applications as number of permits per application is limited · 58 m away
- 801 Barton Springs Level 6 · 801 Barton Springs Propco, LLCOct 28, 2025801 barton springs level 6 (stair infill and corridor) — renovation/alteration — demolition of existing stair and providing infill. creating a common corridor withing existing full floor footprint for spec suites · 58 m away
- 801 Barton Springs Level 7 · 801 Barton Springs Propco, LLCMar 30, 2026801 barton springs level 7 (corridor) — renovation/alteration — spec suite corridor level 7. building core is existing to remain. corridor finish refresh. demolition two doors within building corridor scope to existing building common amenities on the floor. new doors not in scope · 58 m away
- 801 Barton Springs · 801 Barton Springs Propco, LLCMar 30, 2026801 bartonsprings level 7 (unit 725) — renovation/alteration — spec suite on level 7. renovating existing worksharing layout to become spec suite office space with conference room, offices, phone rooms, and support spaces · 58 m away
- 801 Farm To Market 1626 811 Barton Springs Road · Elm Grove EsJan 29, 2024Elm grove es improvements — renovation/alteration — cooler/freezer replacement · 68 m away
- 811 Barton Springs Road · Cpf 811 Barton LLC C/O TranswesternFeb 8, 2024Floor 2 restroom renovation — renovation/alteration — renovation of existing bathrooms within current walls · 68 m away
- 811 Barton Springs Road · Cpf 811 Barton LLCOct 19, 2026Pluckers office remodel — renovation/alteration — remodeling and refinishing an existing space within the occupied office. new partition walls and doors to create enclosed offices and corridor · 68 m away
- 901 Philomena Dr. 811 Barton Springs Road · Fuentes EsJan 29, 2024Fuentes es improvements — renovation/alteration — maintenance asphalt replacement · 68 m away
- 1005 E, Ranch To Market Rd 150 811 Barton Springs Road · Tobias EsJan 29, 2024Tobias es improvements — renovation/alteration — maintenance asphalt, hvac unit, cooler/freezer replacement and roof replacement, fire alarm · 68 m away
- 811 Barton Springs Road · Cpf 811 Barton LLC C/O TranswesternJun 25, 2024Kforce — renovation/alteration — office suite in part of previous single suite · 68 m away
- 3600 FM 967 811 Barton Springs Road · Dahlstrom MsJan 29, 2024Dahlstrom improvements — renovation/alteration — maintenance asphalt replacement, hvac unit replacement · 68 m away
More offices in 78704.