3205 Tom Green St
Austin, TX 78705
Demolition permitted; triplex plans withdrawn at 3205 Tom Green St
Austin records show active permits dated February 12, 2025, for demolishing a two-story duplex and a detached garage at 3205 Tom Green St. Three permits for new three-story triplex units were dated August 28, 2025, but all three are marked withdrawn, so the records do not confirm that the triplex will be built.
Summarized from City of Austin records · updated Aug 28, 2025
- Projects
- 6
- 6 filings
- Latest filing
- Aug 28, 2025
- since Feb 12, 2025
- Largest scope
- —
- Listed value
- —
Where this project stands
Permit withdrawnNew triplex unit 1(a) 3 story 3 bed/ 3.5 bath covered porch and patio
- AppliedAug 29, 2024
- IssuedAug 28, 2025
- !WorkAug '25 – Aug '26
- Final inspection
Marked withdrawn Aug 19, 2026.
2 contacts on this project · 2 phone numbers
Permit & project history
6 projectsNew triplex unit 1(a) 3 story 3 bed/ 3.5 bath covered porch and patio
New triplex unit 1(a) 3 story 3 bed/ 3.5 bath covered porch and patio
City of Austin permitBuilding PermitWithdrawn- Record
- 2024-167849 BP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
New triplex unit 3(c) 3 story 3 bed/3.5 bath covered porch and patio
New triplex unit 3(c) 3 story 3 bed/3.5 bath covered porch and patio
City of Austin permitBuilding PermitWithdrawn- Record
- 2024-167851 BP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
New triplex unit 2(b) 3 story 3 bed/3.5 bath covered porch and patio
New triplex unit 2(b) 3 story 3 bed/3.5 bath covered porch and patio
City of Austin permitBuilding PermitWithdrawn- Record
- 2024-167850 BP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Emergency repair: tree limb damaged cloth risers and they are arcing. replace cloth risers with new rigid riser replace old meter bases with new install 2 new 100 amp disconnects to feed existing panels
Emergency repair: tree limb damaged cloth risers and they are arcing. replace cloth risers with new rigid riser replace old meter bases with new install 2 new 100 amp disconnects to feed existing panels
City of Austin permitElectrical PermitFinal- Record
- 2025-030960 EP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Total demolition of 2-story duplex 1120 sq ft circa 1935. ***the building shall not be demolished until after the contractor has fulfilled the neighbor notification requirements outlined in steps 5 & 6 of the demolition webpage
Total demolition of 2-story duplex 1120 sq ft circa 1935. ***the building shall not be demolished until after the contractor has fulfilled the neighbor notification requirements outlined in steps 5 & 6 of the demolition webpage
City of Austin permitBuilding PermitActive- Record
- 2024-057176 BP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Demolition of detached 1 story detached garage 327.6 sq ft circa 1935. ***the building shall not be demolished until after the contractor has fulfilled the neighbor notification requirements outlined in steps 5 & 6 of the demolition webpage
Demolition of detached 1 story detached garage 327.6 sq ft circa 1935. ***the building shall not be demolished until after the contractor has fulfilled the neighbor notification requirements outlined in steps 5 & 6 of the demolition webpage
City of Austin permitBuilding PermitActive- Record
- 2024-057198 BP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 3205 Tom Green St
What is being built at 3205 Tom Green St?
Three permits described new three-story triplex units, but the permits were withdrawn on August 28, 2025. The records do not confirm that the triplex will be built.
Is the duplex at 3205 Tom Green St being demolished?
An active City of Austin permit dated February 12, 2025, covers demolition of a two-story duplex built around 1935. The permit says demolition must wait until neighbor-notification requirements are fulfilled.
Is the garage at 3205 Tom Green St being demolished?
An active permit dated February 12, 2025, covers demolition of a detached, one-story garage built around 1935. The permit also requires neighbor notification before demolition.
Were triplex permits approved at 3205 Tom Green St?
The City of Austin records list three building permits for triplex units, dated August 28, 2025. All three are marked withdrawn.
What do the triplex plans at 3205 Tom Green St include?
The withdrawn permit descriptions specify three-story units with three bedrooms, 3.5 bathrooms, a covered porch and a patio.
When were permits filed for 3205 Tom Green St?
The demolition permits were dated February 12, 2025. The three permits for triplex units were dated August 28, 2025, and are marked withdrawn.
Also being built nearby
All of 78705- 400 E 32nd StMay 20, 2025Replacement of complete existing central heat and air system with or without duct work · 67 m away
- 3210 Duval StJul 14, 2026Unit c replace gas flex line with hard pipe (approximately 5) · 76 m away
- 3300 Tom Green StApr 24, 2024Upgrade main electrical service · 78 m away
- 3303 Tom Green StJun 19, 2026Gday we need to upgrade an existing duplex service as the incoming line is low and we need to group meters · 80 m away
- 3305 Tom Green StAug 14, 2024Replacement of complete existing central heat and air system with or without duct work · 99 m away
- 3300 Duval StApr 22, 2025Interior remodel: repair and change flat roof to slope - raise roof in rear of home sufficient for insulation and access via existing stairs as approved by the landmark commission · 106 m away
- 3200 Duval StMay 20, 2024Changing out 3 ton airhandler (apt#307) · 106 m away
- 3116 Benelva DrMay 22, 2025Replacement of mini-split system · 142 m away
- 3306 Duval StApr 27, 2026New steel pool with reqd enclosure device for existing 2-story single family residence · 145 m away
- 401 E 34th StApr 30, 2026Addition/remodel. addition of a covered walkway to side of existing noncomplying detached garage. demolish unpermitted rear addition of garage structure · 145 m away
- 3301 Duval StMar 11, 2024Replacement of water heater · 149 m away
- 3305 Duval StMar 17, 2025Total demolition of an adu 1768 sq ft circa 1935 ***the building shall not be demolished until after the contractor has fulfilled the neighbor notification requirements outlined in steps 5 & 6 of the demolition webpage · 157 m away