13101 Tesla Rd
Austin, TX 78725 · Erik Mansell
Giga Texas East Parking Structure approved in Austin
A site plan for the Giga Texas East Parking Structure was approved and released by the City of Austin on June 18, 2026. A separate site plan called Giga Texas-Ecological Paradise was in review as of November 13, 2026, and private access road and drainage improvements were approved and released on February 3, 2026.
Summarized from City of Austin, Texas Department of Licensing and Regulation records · updated Nov 18, 2026
- Projects
- 9
- 9 filings
- Latest filing
- Nov 18, 2026
- since Nov 18, 2026
- Largest scope
- —
- Estimated cost
- $50K
- state registration
Where this project stands
Permit active · work underwayEtj - installation of 24 reclaimed water line (5560 lf) and 18 wastewater line (5170 lf). sp-2026-0021.etjx
- AppliedMay 20, 2026
- IssuedMay 20, 2026
- WorkMay '26 – Nov '26
- Final inspection
1 contact on this project · 1 phone number
Permit & project history
9 projectsEtj - installation of 24 reclaimed water line (5560 lf) and 18 wastewater line (5170 lf). sp-2026-0021.etjx
Etj - installation of 24 reclaimed water line (5560 lf) and 18 wastewater line (5170 lf). sp-2026-0021.etjx
City of Austin permitPlumbing PermitActive- Record
- 2026-064079 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
1,743,000 sq ft, ground up and complete interior finish out of the ev manufacturing facility. — tesla gigafactory texas
TDLR project registrationNew ConstructionReview Complete1,743,000 sq ft$50K est.- Project #
- TABS2025001407
- Tenant / owner
- East Parking Garage
- Design firm
- Pro
- Contact
- Pro
Sources: City of Austin · Texas Department of Licensing and Regulation
Questions about 13101 Tesla Rd
What is being built at 13101 Tesla Rd in Austin?
City of Austin records show a site plan for the Giga Texas East Parking Structure, approved and released June 18, 2026. Separate records show access road and drainage improvements at the address.
Is the Giga Texas East Parking Structure approved?
Yes. The City of Austin site plan case, 13644567, was approved and released on June 18, 2026.
What is the Giga Texas-Ecological Paradise project?
It is the name of a City of Austin site plan case at 13101 Tesla Rd. The case was in review as of November 13, 2026.
Are road or drainage improvements planned at 13101 Tesla Rd?
A City of Austin case for private access road and drainage improvements was approved and released on February 3, 2026. The case number is 12688819.
When will the East Parking Structure open?
The City of Austin records provided list a site plan approval date of June 18, 2026, but do not give an opening date.
What utility work is recorded at 13101 Tesla Rd?
An active plumbing permit filed May 20, 2026, covers installation of reclaimed water and wastewater lines in the ETJ. The permit number is 2026-064079 PP.