Rooftop solar and energy storage permitted at 12412 Mallard Ln

A 9.775 kW rooftop solar system and 27 kW energy storage system are being installed at the existing residence at 12412 Mallard Ln. The City of Austin issued the electrical permit on November 7, 2025, followed by a permit to upgrade the main distribution panel on November 12, 2025.

Summarized from City of Austin records · updated Nov 12, 2025

Projects
2
2 filings
Latest filing
Nov 12, 2025
since Nov 7, 2025
Largest scope
—
Listed value
—

Where this project stands

Finaled

Disconnect/reconnect to upgrade main distribution panel

  1. AppliedNov 7, 2025
  2. IssuedNov 12, 2025
  3. WorkNov '25 – Jan '26
  4. Final inspectionJan 13, 2026

Passed final inspection Jan 13, 2026.

1 contact on this project · 1 phone number

Permit & project history

2 projects
  1. Disconnect/reconnect to upgrade main distribution panel

    Disconnect/reconnect to upgrade main distribution panel

    City of Austin permitElectrical PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. Install new 9.775 kw rooftop solar system and 27kw energy storage system for existing residential only

    Install new 9.775 kw rooftop solar system and 27kw energy storage system for existing residential only

    City of Austin permitElectrical PermitFinal
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Austin

Questions about 12412 Mallard Ln

What is being built at 12412 Mallard Ln?

City of Austin records show a rooftop solar system and energy storage system being installed at the existing residence. The solar system is listed at 9.775 kW and the energy storage system at 27 kW.

Is a new house being built at 12412 Mallard Ln?

The permit describes the solar and energy storage work as being for an existing residence. The records provided do not show a new home construction permit.

When was the solar permit filed at 12412 Mallard Ln?

The City of Austin electrical permit, 2025-140276 EP, was filed on November 7, 2025, for the rooftop solar and energy storage installation.

What size solar system is planned at 12412 Mallard Ln?

Permit 2025-140276 EP lists a new 9.775 kW rooftop solar system and a 27 kW energy storage system.

Is the electrical panel being upgraded at 12412 Mallard Ln?

Yes. City of Austin permit 2025-143783 EP, filed November 12, 2025, covers disconnecting and reconnecting power to upgrade the main distribution panel.