Rodriguez Elementary renovations include a mental health center
Renovation work at Rodriguez Elementary School includes converting an existing classroom into a mental health center, upgrading four pre-K classrooms, HVAC improvements and roof repairs. The project was registered with TDLR on August 9, 2024, under project number TABS2024025158. The applicant’s estimated project cost is $1.5 million.
Summarized from Texas Department of Licensing and Regulation records · updated Aug 9, 2024
- Projects
- 1
- 1 filings
- Latest filing
- Aug 9, 2024
- since Aug 9, 2024
- Largest scope
- 16,525 sf
- Estimated cost
- $1.5M
- state registration
Where this project stands
CompletedAISD Renovations at Rodriguez Elementary School
16,525 sq ft · $1.5M est.
- RegisteredAug 9, 2024
- Plan review
- ConstructionJan '25 – Aug '25
- Inspected
- Closed
Ran as a 7-month build.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectConvert existing classroom to mental health center, upgrade (4) pre-k classrooms, hvac improvements and roof repairs. — rodriguez elementary school
TDLR project registrationRenovation/AlterationProject Closed16,525 sq ft$1.5M est.- Project #
- TABS2024025158
- Tenant / owner
- Aisd Renovations At Rodriguez Elementary School
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 4400 Franklin Park Drive
What is being built at 4400 Franklin Park Drive?
The project at Rodriguez Elementary School includes converting an existing classroom into a mental health center, upgrading four pre-K classrooms, HVAC improvements and roof repairs.
Is Rodriguez Elementary getting a mental health center?
A TDLR project registration describes converting an existing classroom at the school into a mental health center. The project was registered on August 9, 2024.
When was the Rodriguez Elementary renovation registered?
The project was registered with the Texas Department of Licensing and Regulation on August 9, 2024. Its project number is TABS2024025158.
How much will the Rodriguez Elementary project cost?
The applicant estimated the project cost at $1.5 million. This is an estimate for the project, not a reported final cost.
How large is the Rodriguez Elementary renovation?
The TDLR registration lists the project at 16,525 square feet and describes it as a renovation or alteration.
Is the Rodriguez Elementary renovation project complete?
The TDLR record lists the project status as “Project Closed.”
Also being built nearby
All of 78744- 5004 Allyson CtDec 21, 2023Replace interior hot and cold water lines with uponor pex pipe. replace main water line form city lead to home · 98 m away
- 5002 Joshua CtDec 28, 2023Water heater replacement like for like · 99 m away
- 5005 Allyson CtJul 12, 2024Replacement of an existing water heater · 100 m away
- 4501 Eric CirSep 23, 2025Will replace meter boxbreaker box new ground rods · 110 m away
- 5007 Allyson CtJun 25, 2024Emergency repair per tx gas- relocate gas meter away from a/c windows & doorway while tx gas repairs leak · 114 m away
- 4507 Franklin Park DrMay 17, 2024Express: existing foundation repair as per scope of work attached · 146 m away
- 5005 Joshua CtApr 21, 202515 tunnel · 154 m away
- 5008 Michelle CtNov 13, 2025Replacement of complete existing central heat and air system with or without duct work · 175 m away
- 5003 S Pleasant Valley RdFeb 25, 2026Express- replace 5 existing windows with new windows of the same size; like for like install · 181 m away
- 4600 Franklin Park DrMar 25, 2026Replacing existing sewer line in yard only and installing clean out near house. original sewer line is schedule 35 and has multiple issues. piping to be replaced with schedule 40 pvc with installation of clean out adjacent to home · 193 m away
- 4505 Union CirDec 27, 2024Updated existing electrical main panel with a new main breaker panel. meter has been removed by austin energy · 202 m away
- 4601 Cedargrove DrApr 26, 2024Partial demolition garage conversion to kitchen/living space interior remodel and new rear covered patio addition · 203 m away