groundranger
Recent · latest filing Sep 2025Commercial

5000 S IH 35 Svrd Sb

Austin, TX 78745

EV charging upgrades permitted at 5000 S IH 35

Austin permits filed April 25, 2025, cover converting six parking stalls into two Level 2 and four Level 3 EV stalls, adding four Level 2 charging outlets in a service garage, and replacing two Level 2 EV chargers. A September 24, 2025, electrical permit covers one set of individually mounted illuminated letters on the front wall. The listed permits are marked final.

Summarized from City of Austin records · updated Sep 24, 2025

Projects
5
5 filings
Latest filing
Sep 24, 2025
since Nov 16, 2023
Largest scope
—
Listed value
—

Where this project stands

Finaled

Ford group 1 of south austin - install one (1) set of individually mounted lit letters on front wall

  1. AppliedSep 23, 2025
  2. IssuedSep 24, 2025
  3. WorkSep '25 – Jun '26
  4. Final inspectionJun 23, 2026

Passed final inspection Jun 23, 2026.

Permit & project history

5 projects
  1. Ford group 1 of south austin - install one (1) set of individually mounted lit letters on front wall

    Ford group 1 of south austin - install one (1) set of individually mounted lit letters on front wall

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. (6) standard parking stalls are to be converted into (2) standard level-2 electric vehicle (ev) parking stalls and (4) level-3 ev parking stalls. (4) level-2 ev charging outlets will be installed in the service garage. (2) level-2 evcs will be replaced with new

    (6) standard parking stalls are to be converted into (2) standard level-2 electric vehicle (ev) parking stalls and (4) level-3 ev parking stalls. (4) level-2 ev charging outlets will be installed in the service garage. (2) level-2 evcs will be replaced with new

    City of Austin permitBuilding PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  3. (6) standard parking stalls are to be converted into (2) standard level-2 electric vehicle (ev) parking stalls and (4) level-3 ev parking stalls. (4) level-2 ev charging outlets will be installed in the service garage. (2) level-2 evcs will be replaced with new. building ev

    (6) standard parking stalls are to be converted into (2) standard level-2 electric vehicle (ev) parking stalls and (4) level-3 ev parking stalls. (4) level-2 ev charging outlets will be installed in the service garage. (2) level-2 evcs will be replaced with new. building ev

    City of Austin permitElectrical PermitFinal
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  4. We will be installing 3 200kw cp power link dcfc stations 3 dual cp6000 19.2kw lvl 2 stations 1 cph50 1 cpf50 and 10 nema 14-50 outlets. 2 existing lvl 2 stations will be retrofitted for the sd and nvd area stations

    We will be installing 3 200kw cp power link dcfc stations 3 dual cp6000 19.2kw lvl 2 stations 1 cph50 1 cpf50 and 10 nema 14-50 outlets. 2 existing lvl 2 stations will be retrofitted for the sd and nvd area stations

    City of Austin permitElectrical PermitExpired
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  5. We will be installing 3 200kw cp power link dcfc stations 3 dual cp6000 19.2kw lvl 2 stations 1 cph50 1 cpf50 and 10 nema 14-50 outlets. 2 existing lvl 2 stations will be retrofitted for the sd and nvd area stations

    We will be installing 3 200kw cp power link dcfc stations 3 dual cp6000 19.2kw lvl 2 stations 1 cph50 1 cpf50 and 10 nema 14-50 outlets. 2 existing lvl 2 stations will be retrofitted for the sd and nvd area stations

    City of Austin permitBuilding PermitExpired
    Tenant / owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Austin

Questions about 5000 S IH 35 Svrd Sb

What is being built at 5000 S IH 35 Svrd Sb in Austin?

Permits indicate EV parking and charging upgrades, along with illuminated letters on the front wall. The records do not specify a broader construction project.

Are EV chargers being added at 5000 S IH 35?

Yes. A permit filed April 25, 2025, covers two Level 2 and four Level 3 EV parking stalls, four Level 2 charging outlets in the service garage, and replacement of two Level 2 chargers.

How many EV parking stalls are planned at 5000 S IH 35?

The April 25, 2025, permit describes converting six standard stalls into two Level 2 and four Level 3 EV stalls.

What do the permits say about signage at 5000 S IH 35?

An electrical permit filed September 24, 2025, covers one set of individually mounted illuminated letters on the front wall. The permit description calls this “Ford group 1 of south austin.”

When were permits filed for work at 5000 S IH 35?

The EV charging permits were filed April 25, 2025. The electrical permit for illuminated letters was filed September 24, 2025.

What are the permit numbers for work at 5000 S IH 35?

The EV charging permits are 2025-049085 BP and 2025-049085 EP. The permit for illuminated letters is 2025-119735 EP.

Also being built nearby

All of 78745

More parking structures in 78745.

Email me when a new permit is filed