groundranger
Recent · latest filing Oct 2025Residential

5 Cicero Ln

Austin, TX 78746

45.5-kW solar system with three battery units

City of Austin permits filed September 8 and October 2, 2025, indicate a 45.5-kW solar system with 100 455-watt panels and three Tesla Powerwall batteries at 5 Cicero Ln. A separate electrical permit was filed to connect the batteries to the grid. Both permits are listed as expired.

Summarized from City of Austin records · updated Oct 2, 2025

Projects
2
2 filings
Latest filing
Oct 2, 2025
since Sep 8, 2025
Largest scope
—
Listed value
—

Where this project stands

Permit expired

Need this permit to connect the batteries with the grid

  1. AppliedSep 10, 2025
  2. IssuedOct 2, 2025
  3. !WorkOct '25 – Mar '26
  4. Final inspection

Marked expired Apr 1, 2026.

1 contact on this project · 1 phone number

Permit & project history

2 projects
  1. Need this permit to connect the batteries with the grid

    Need this permit to connect the batteries with the grid

    City of Austin permitElectrical PermitExpired
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro
  2. We are installing 45.5kw solar system with 100 canadian 455w solar panel and 3 tesla powerwall batteries

    We are installing 45.5kw solar system with 100 canadian 455w solar panel and 3 tesla powerwall batteries

    City of Austin permitElectrical PermitExpired
    Owner
    Pro
    Contractor
    Pro
    Contact
    Pro

Sources: City of Austin

Questions about 5 Cicero Ln

What is being installed at 5 Cicero Ln in Austin?

A City of Austin permit describes a 45.5-kW solar system with 100 455-watt panels and three Tesla Powerwall batteries. A separate permit covers connecting the batteries to the grid.

How many solar panels are planned for 5 Cicero Ln?

The September 8, 2025, permit description lists 100 455-watt solar panels.

Are batteries included in the solar project at 5 Cicero Ln?

Yes. The permit description lists three Tesla Powerwall batteries, and an October 2, 2025, electrical permit covers connecting the batteries to the grid.

When were permits filed for the solar system at 5 Cicero Ln?

The solar-system electrical permit, 2025-107870 EP, was filed September 8, 2025. The battery grid-connection permit, 2025-115283 EP, was filed October 2, 2025.

Are the permits for 5 Cicero Ln still active?

No. Both City of Austin electrical permits, 2025-107870 EP and 2025-115283 EP, are listed as expired.