12100 Samsung Blvd
Austin, TX 78754 · Sas Fire Water Pump Building - Diesel Generator, Sas Gcs Capa-Up - Tior06 & Tior10 Demo + 36 more
Generator support work and equipment upgrades at industrial center
A concrete maintenance-access pad and offload containment for a diesel generator are the latest registered work at this multi-tenant industrial center, filed October 28, 2026. Other records indicate equipment changes inside manufacturing facilities, including installations and demolitions. A site plan for a parking garage was approved and released on July 13, 2026.
Summarized from Texas Department of Licensing and Regulation, City of Austin records · updated Oct 28, 2026
- Projects
- 103
- 103 filings
- Latest filing
- Oct 28, 2026
- since Mar 2, 2007
- Largest scope
- 1,315,000 sf
- Estimated cost
- $38M
- state registration
Where this project stands
In state plan reviewSAS Fire Water Pump Building - Diesel Generator
4,000 sq ft · $350K est.
- RegisteredOct 28, 2026
- Plan reviewnow
- ConstructionMay '27 – Aug '27
- Inspected
- Closed
Construction is scheduled to start May 24, 2027. Subcontractors and suppliers are usually picked in the weeks before.
4 contacts on this project · 3 phone numbers
Permit & project history
103 projectsInstallation of a concrete maintenance access platform pad for a diesel generator and associated offload containment to support the fire water pump building. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationProject Registered4,000 sq ft$350K est.- Project #
- TABS2027004602
- Tenant / owner
- Sas Fire Water Pump Building - Diesel Generator
- Design firm
- Pro
- Contact
- Pro
Demolition and replacement of heat gen fan h, its damper, and associated ductwork. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationProject Registered20,000 sq ft$1.7M est.- Project #
- TABS2027004187
- Tenant / owner
- Pro
- Design firm
- Pro
- Contact
- Pro
Demolition of idle gcs gas equipment (dtlrs), three (3) offline htb dtlrs, two (2) octane dtlrs, located f2m1 csf col. j22-k22. 1. as-htb-01d-d, 2. as-htb-02d-d, 3.as-htb-03d-d, 4. as-octane-01d-d, 5.as-octane-02d-d — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete500 sq ft$300K est.- Project #
- TABS2027002546
- Tenant / owner
- Sas Gcs Capa-Up - Tior06 & Tior10 Demo
- Design firm
- Pro
- Contact
- Pro
Install fab1 icpms in the fab1 acid room (c9) and all necessary utilities, install hf(49%) remote sampling cabinet in fab1 acid room (c9) — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete3,098 sq ft$810K est.- Project #
- TABS2027002241
- Tenant / owner
- Sas 2026 Capital Projects - Fab1 Icpms
- Design firm
- Pro
- Contact
- Pro
Interior remodel existing light manufacturing facility - fab1 tmah replacement - f126-ch01
Interior remodel existing light manufacturing facility - fab1 tmah replacement - f126-ch01
City of Austin permitBuilding PermitActive- Record
- 2026-119503 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Qty x2 new wf6 gas cabinets in the fab 2 fsf east bunker to support qty x1 new metals (snnr04) install qty (4) teos dtlrs, qty (1) teos lvmb for new tior06 + tior10 tools. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete800 sq ft$1.7M est.- Project #
- TABS2027000140
- Tenant / owner
- Pro
- Design firm
- Pro
- Contact
- Pro
F1 esc784(3%) blender and distribution install, acuplane blender and distribution loop install. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete2,070 sq ft$1.7M est.- Project #
- TABS2026026745
- Tenant / owner
- Sas Fab1 Chemical Blenders
- Design firm
- Pro
- Contact
- Pro
Installation of new f1-tmah (2.38%)-c12-01d-p, and new tmah(2.38%) storage tank. installation of new distribution : (4) t-boxes, (6) vmbs. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete3,000 sq ft$1.8M est.- Project #
- TABS2026026316
- Tenant / owner
- Sas Fab1 Tmah Replacement
- Design firm
- Pro
- Contact
- Pro
Installation of new slurry blender and distribution loops. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete1,100 sq ft$2.5M est.- Project #
- TABS2026025560
- Tenant / owner
- Sas Fab2 Slurry Blender
- Design firm
- Pro
- Contact
- Pro
Demolish equipment one (1) dtlr to make space for new equipment and new tool in fab 1 csf. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete4,900 sq ft$150K est.- Project #
- TABS2026022996
- Tenant / owner
- Sas Gcs Capa Up Demo F126-Sg01
- Design firm
- Pro
- Contact
- Pro
Demolition of idle slurry equipment and distribution loops in fab1 slurry and unused vmb f1-esc784-f6-01v-w in fab1 csf — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete1,660 sq ft$800K est.- Project #
- TABS2026019994
- Tenant / owner
- Sas Fab1 Slurry Blender Demo
- Design firm
- Pro
- Contact
- Pro
Move-in and set eight (8) new teos dtlrs, one (1) lvmb, one (1) transfer line from as-teos-01mbcd-c-04, located f2m1 csf col. f20 — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete13,125 sq ft$1.7M est.- Project #
- TABS2026015790
- Tenant / owner
- Sas Gcs Capa Up Install F226-Sg03
- Design firm
- Pro
- Contact
- Pro
Install new remote ev controller for s-c4f6-205a/b-e heater blankets and install + wire new heater blankets compatible with remote ev controller for s-c4f6-205a/b-e — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete1,068 sq ft$161K est.- Project #
- TABS2026015791
- Tenant / owner
- Sas Gcs Capa Up Install F226-Sg04
- Design firm
- Pro
- Contact
- Pro
Install qty x2 new wf6 gas cabinets in the fab2 fsf east bunker to support qty x1 new metals (snnr02) tool for 14k lpv — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete856 sq ft$645K est.- Project #
- TABS2026015792
- Tenant / owner
- Sas Gcs Capa Up Install F226-Sg05
- Design firm
- Pro
- Contact
- Pro
Replacement of existing steam to hot water heat exchanger skid system; building footprint remains unchanged
Replacement of existing steam to hot water heat exchanger skid system; building footprint remains unchanged
City of Austin permitMechanical PermitActive- Record
- 2025-082904 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Demolition of idle gcs equipment's *dtlrs), 10 offline teos dtlrs, located f2m1 csf col.f20. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete13,621 sq ft$400K est.- Project #
- TABS2026012573
- Tenant / owner
- Sas Gcs Capa Up Demo F226-Sg01
- Design firm
- Pro
- Contact
- Pro
Demolition of 7 idle gvs gas equipment located f2m2 csf, near columns g2-h2 and e5-h5. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete6,734 sq ft$442K est.- Project #
- TABS2026012576
- Tenant / owner
- Sas Gcs Capa Up Demo F226-Sg02
- Design firm
- Pro
- Contact
- Pro
Design and installation of (1) t-box and (1) vmb within the fab2 csf to expand the existing tmah(2.38%) distribution in fab2. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete2,000 sq ft$630K est.- Project #
- TABS2026011617
- Tenant / owner
- Sas Fab2 Clns Tmah Conversion
- Design firm
- Pro
- Contact
- Pro
Scope consists of issuing ifc set and providing ca for a permanent swing tank within a new containment area connected to the original fab1 fww and aww transfer tank containment. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationReview Complete3,750 sq ft$12M est.- Project #
- TABS2026008869
- Tenant / owner
- Sas Fab1 Waste Tank Expansion
- Design firm
- Pro
- Contact
- Pro
Installation of (1) new sif4 gas cabinet within the fab2 corrosive/oxidizer room and (1) new vmb within the fab2 csf area. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationProject Closed3,207 sq ft$3.8M est.- Project #
- TABS2026008035
- Tenant / owner
- Sas Fab2 Sif4 Distribution
- Design firm
- Pro
- Contact
- Pro
Replacement of existing steam to hot water heat exchanger skid system; building footprint remains unchanged
Replacement of existing steam to hot water heat exchanger skid system; building footprint remains unchanged
City of Austin permitElectrical PermitFinal- Record
- 2025-082904 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Installation for a new cuso4 tank within the fab1 crs room. the new tank will be installed on top of existing containment trench grating. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationProject Closed1,215 sq ft$280K est.- Project #
- TABS2026003000
- Tenant / owner
- Sas Fab1 Cuso4 Tank Replacement
- Design firm
- Pro
- Contact
- Pro
Construction of steel canopies over approximately 1112 existing parking spaces. (reactivated after revision expanded the scope of project)
Construction of steel canopies over approximately 1112 existing parking spaces. (reactivated after revision expanded the scope of project)
City of Austin permitElectrical PermitFinal- Record
- 2024-096883 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Replacement of existing boilers deaerator combustion air system; building footprint remains unchanged
Replacement of existing boilers deaerator combustion air system; building footprint remains unchanged
City of Austin permitElectrical PermitActive- Record
- 2025-122339 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Replacement of cub1 non-heated air dryers and conditioning of cub1 compressor room; building footprint remains unchanged
Replacement of cub1 non-heated air dryers and conditioning of cub1 compressor room; building footprint remains unchanged
City of Austin permitPlumbing PermitFinal- Record
- 2024-052937 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Replacement of existing steam to hot water heat exchanger skid system; building footprint remains unchanged
Replacement of existing steam to hot water heat exchanger skid system; building footprint remains unchanged
City of Austin permitBuilding PermitActive- Record
- 2025-082904 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expand mechanical room at existing semiconductor manufacturing
Expand mechanical room at existing semiconductor manufacturing
City of Austin permitMechanical PermitFinal- Record
- 2021-003861 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expand mechanical room at existing semiconductor manufacturing
Expand mechanical room at existing semiconductor manufacturing
City of Austin permitBuilding PermitFinal- Record
- 2021-003861 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expand waste tank room at existing semiconductor manufacturing
Expand waste tank room at existing semiconductor manufacturing
City of Austin permitMechanical PermitFinal- Record
- 2020-175119 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expand waste tank room at existing semiconductor manufacturing
Expand waste tank room at existing semiconductor manufacturing
City of Austin permitElectrical PermitFinal- Record
- 2020-175119 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expand mechanical room at existing semiconductor manufacturing
Expand mechanical room at existing semiconductor manufacturing
City of Austin permitPlumbing PermitFinal- Record
- 2021-003861 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expand mechanical room at existing semiconductor manufacturing
Expand mechanical room at existing semiconductor manufacturing
City of Austin permitElectrical PermitFinal- Record
- 2021-003861 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expand waste tank room at existing semiconductor manufacturing
Expand waste tank room at existing semiconductor manufacturing
City of Austin permitBuilding PermitFinal- Record
- 2020-175119 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Expand waste tank room at existing semiconductor manufacturing
Expand waste tank room at existing semiconductor manufacturing
City of Austin permitPlumbing PermitFinal- Record
- 2020-175119 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Temporary building permit-scope of permit is limited to foundation slab on grade and underground utilities for pr 2024-093191
Temporary building permit-scope of permit is limited to foundation slab on grade and underground utilities for pr 2024-093191
City of Austin permitBuilding PermitExpired- Record
- 2024-148413 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
New canopy photometrics plan - west yard photometrics plan - installing 11 new lights poles
New canopy photometrics plan - west yard photometrics plan - installing 11 new lights poles
City of Austin permitElectrical PermitFinal- Record
- 2025-069527 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Installation of (2) wf6 gas cabinets and associated piping within the fab2 fsf gas bunker. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationInspection Complete250 sq ft$600K est.- Project #
- TABS2025016139
- Tenant / owner
- Sas Fab2 Teos Infrastructure - Phase 2
- Design firm
- Pro
- Contact
- Pro
Installation of (2) teos dtlrs and associated piping within the fab2 csf. — samsung austin semiconductor
TDLR project registrationNew ConstructionInspection Complete150 sq ft$1.2M est.- Project #
- TABS2025015096
- Tenant / owner
- Sas Fab2 Teos Infrastructure - Phase 1
- Design firm
- Pro
- Contact
- Pro
Demolition of (2) teos dtlrs and (1) teos vmb and associated piping within the fab2 csf. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationInspection Complete145 sq ft$500K est.- Project #
- TABS2025013835
- Tenant / owner
- Sas Fab2 Teos Demo Phase II
- Design firm
- Pro
- Contact
- Pro
+ 63 older projects. See the full history with a free trial.
Sources: Texas Department of Licensing and Regulation · City of Austin
Questions about 12100 Samsung Blvd
What is being built at 12100 Samsung Blvd?
The latest registration, dated October 28, 2026, describes a concrete maintenance-access pad and offload containment for a diesel generator supporting a fire-water pump building. It is listed as a renovation or alteration, not a new building.
When was the latest project filed at 12100 Samsung Blvd?
The latest listed registration is dated October 28, 2026. It is TDLR project TABS2027004602 for the SAS Fire Water Pump Building - Diesel Generator.
Is a parking garage planned at 12100 Samsung Blvd?
A City of Austin site plan for a Samsung Austin Semiconductor parking garage was approved and released on July 13, 2026. The record provided does not establish that construction has started.
What other construction work is happening at the industrial center?
Recent registrations include chemical and slurry blender installations, gas equipment demolition, and upgrades to manufacturing-facility systems. For example, a chemical blenders project was registered August 3, 2026, as TABS2026026745.
Is a new semiconductor fab being built at 12100 Samsung Blvd?
The records listed here describe alterations and equipment work inside existing manufacturing facilities, along with a parking garage site plan. They do not identify a new fab building.
What's being built near Torchy's Tacos on East Parmer Lane?
The 12100 Samsung Blvd records concern industrial-site work. Torchy's Tacos is about 427 meters away, at 3500 East Parmer Lane; its separate renovation and restaurant finish-out record was filed August 27, 2026.
Also being built nearby
All of 78754- 3500 East Parmer Ln · Rh Pioneer North, LLCFeb 9, 2024Swish east village — renovation/alteration — medical office interior remodel · 427 m away
- 3500 E Parmer Lane · Rh Ra-7 Commercial Qozb LLCSep 30, 2026Dave's hot chicken -austin tx — renovation/alteration — a new tenant finish out of a stand alone building along with improvements to accommodate a 2752 sq ft daves hot chicken · 427 m away
- 3500 E Parmer Ln · Janis Atx LLCNov 12, 20264325 sq ft commercial lease space build-out for nail salon · 427 m away
- 3500 East Palmer Lane · Rh Ra-7 Commercial Qozb LLCSep 16, 2025Potbelly sandwich works — renovation/alteration — commercial tenant improvements to an existing building consisting of 1,900 sq ft, incorporating potbelly design standards · 427 m away
- 3500 East Parmer Lane · Rh Ra-7 Commercial Qozb, LLCAug 27, 2026Torchy's tacos — renovation/alteration — tenant interior finish-out for restaurant · 427 m away
- 3500 E Palmer Lane · Eastvillage Land AtxDec 29, 2025Shake shack 1741 east village — new construction — interior fitout for new quick service shake shack restaurant with drive thru · 427 m away
- 3124-1/2 Parmer LnJul 21, 2026East village estoria lane · 430 m away
- 3101 Yager LnFeb 3, 2026Eastvillage ra 2, 3 commercial · 494 m away
- 12301 Innovar CirMar 2, 2007Pioneer crossing golf course (resubmittal of sp-03-0109d) · 540 m away
- 3001 E Yager LnSep 8, 2025The scope of work is the installation of onsite underground domestic water line piping and wastewater piping. ref: sp-2020-0338c · 556 m away
- 11909 Samsung BlvdFeb 3, 2021Jourdan crossing phase c, section 2 · 573 m away
- 3500 Parmer LnOct 2, 2026Eastvillage towncenter · 580 m away
More demolitions in 78754, warehouses & industrial in 78754, parking structures in 78754.