12100 Samsung Blvd, Austin, TX 78754
Austin, TX 78754 · Samsung Austin Semiconductor
Security upgrades planned for Samsung Austin fab doors
A security project at Samsung Austin Semiconductor involves door hardware modifications and security upgrades throughout fab1 and fab2. The project was registered with the Texas Department of Licensing and Regulation on April 16, 2025; the applicant estimated its cost at $2.4 million.
Summarized from Texas Department of Licensing and Regulation records · updated Apr 16, 2025
- Projects
- 1
- 1 filings
- Latest filing
- Apr 16, 2025
- since Apr 16, 2025
- Largest scope
- 5,400 sf
- Estimated cost
- $2.4M
- state registration
Where this project stands
CompletedSAS 2024 Security Projects- Phase 2
5,400 sq ft · $2.4M est.
- RegisteredApr 16, 2025
- Plan review
- ConstructionApr '25 – Sep '25
- Inspected
- Closed
Ran as a 5-month build.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectDoor hardware modifications and security upgrades to doors throughout fab1 and fab2. — samsung austin semiconductor
TDLR project registrationRenovation/AlterationProject Closed5,400 sq ft$2.4M est.- Project #
- TABS2025016792
- Tenant / owner
- Sas 2024 Security Projects- Phase 2
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 12100 Samsung Blvd, Austin, TX 78754
What is being built at 12100 Samsung Blvd?
The project involves door hardware modifications and security upgrades throughout fab1 and fab2 at Samsung Austin Semiconductor. It is a renovation and alteration project, not a new building.
What are the security upgrades at Samsung Austin Semiconductor?
The project description lists door hardware modifications and security upgrades to doors throughout fab1 and fab2. It was registered with TDLR on April 16, 2025.
When was the Samsung Austin security project filed?
The TDLR project registration is dated April 16, 2025. Its project number is TABS2025016792.
How much will the Samsung Austin security project cost?
The applicant estimated the project cost at $2.4 million in its TDLR registration. This is an estimate for the project, not a reported total construction cost.
Is Samsung building a new facility at 12100 Samsung Blvd?
The record describes door hardware modifications and security upgrades at fab1 and fab2, not construction of a new facility. TDLR lists the work as a renovation or alteration.