12520 Harris Branch Pkwy
Austin, TX 78754
62,435-square-foot light manufacturing facility planned
A 62,435-square-foot light manufacturing facility is planned at 12520 Harris Branch Parkway in Austin. Building, electrical, mechanical and plumbing permits dated August 13–18, 2026, describe ground-up construction with structural steel tilt-wall construction, site work and interior finish-out; the permits are active. The HYE Austin Project site plan was approved and released on October 27, 2026.
Summarized from City of Austin records · updated Oct 27, 2026
- Projects
- 9
- 9 filings
- Latest filing
- Oct 27, 2026
- since Nov 19, 2025
- Largest scope
- —
- Listed value
- —
Where this project stands
Permit active · work underway62435 sq ft ground up new light manufacturer. project will be structural steel tilt wall construction with associated site work and interior finish out
- AppliedMay 18, 2026
- IssuedAug 18, 2026
- WorkAug '26 – Apr '27
- Final inspection
1 contact on this project · 1 phone number
Permit & project history
9 projects62435 sq ft ground up new light manufacturer. project will be structural steel tilt wall construction with associated site work and interior finish out
62435 sq ft ground up new light manufacturer. project will be structural steel tilt wall construction with associated site work and interior finish out
City of Austin permitPlumbing PermitActive- Record
- 2026-104278 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
62435 sq ft ground up new light manufacturer. project will be structural steel tilt wall construction with associated site work and interior finish out
62435 sq ft ground up new light manufacturer. project will be structural steel tilt wall construction with associated site work and interior finish out
City of Austin permitElectrical PermitActive- Record
- 2026-104278 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
62435 sq ft ground up new light manufacturer. project will be structural steel tilt wall construction with associated site work and interior finish out
62435 sq ft ground up new light manufacturer. project will be structural steel tilt wall construction with associated site work and interior finish out
City of Austin permitMechanical PermitActive- Record
- 2026-104278 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
New dumpster enclosure for new light manufacturing facility. (323 sq ft)
New dumpster enclosure for new light manufacturing facility. (323 sq ft)
City of Austin permitBuilding PermitActive- Record
- 2026-104279 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
62435 sq ft ground up new light manufacturer. project will be structural steel tilt wall construction with associated site work and interior finish out
62435 sq ft ground up new light manufacturer. project will be structural steel tilt wall construction with associated site work and interior finish out
City of Austin permitBuilding PermitActive- Record
- 2026-104278 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Installation of the onsite underground water line piping and wastewater piping. approx 500 lf of 6 ww and 120 lf of 2.5 water
Installation of the onsite underground water line piping and wastewater piping. approx 500 lf of 6 ww and 120 lf of 2.5 water
City of Austin permitPlumbing PermitActive- Record
- 2026-089395 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Installation of the onsite fire line piping ref: sp-2021-0447c
Installation of the onsite fire line piping ref: sp-2021-0447c
City of Austin permitPlumbing PermitActive- Record
- 2026-090432 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 12520 Harris Branch Pkwy
What is being built at 12520 Harris Branch Parkway?
Austin permit records describe a new 62,435-square-foot light manufacturing facility. The building permit, 2026-104278 BP, was dated August 13, 2026, and is active.
How large is the planned facility at 12520 Harris Branch Parkway?
The permit description gives the facility size as 62,435 square feet.
When was the light manufacturing facility permitted?
The building permit was dated August 13, 2026. Related electrical and mechanical permits were dated August 14, and the plumbing permit was dated August 18; all are listed as active.
Has the HYE Austin Project site plan been approved?
Yes. Austin case 12840132, dated October 27, 2026, lists the HYE Austin Project site plan as approved and released.
What construction is planned near Opmobility Restroom Renovation?
About 100 meters from the Opmobility Restroom Renovation at 12621 Harris Branch Parkway, permits describe a new 62,435-square-foot light manufacturing facility at 12520 Harris Branch Parkway.
Does the project include a dumpster enclosure?
Yes. Active building permit 2026-104279 BP, dated August 13, 2026, describes a 323-square-foot dumpster enclosure for the new light manufacturing facility.
What site utility work is included at 12520 Harris Branch Parkway?
Permits dated July 14 and 17, 2026, describe onsite fire-line piping and underground water and wastewater piping.
Also being built nearby
All of 78754- 12621 Harris Branch Parkway · Lfr3 Aus Harris Branch LLCJul 20, 2026Opmobility restroom renovation — renovation/alteration — renovation of existing common use bathrooms (680 square feet) · 100 m away
- 12651 Harris Branch Parkway · Lfr3 Aus Harris Branch LLCSep 27, 2024Hbpo transformer — renovation/alteration — interior renovations only in an existing building, electrical, and life safety. 76301sf · 136 m away
- 12555 Harris Branch PkwyMar 10, 2022Commerce park at harris branch park section 1 - nam · 166 m away
- 12408 Harris Branch PkwyAug 11, 2014Harris parmer crossing lots 1-4; amended plat · 172 m away
- 5633 Colinton AveAug 5, 2026Replacement of complete existing central heat and air system with or without duct work replacement of hvac system · 295 m away
- 5609 Colinton AveAug 5, 2024Replacement of complete existing central heat and air system with or without duct work · 316 m away
- 5620 Liberton LnMar 9, 2026Express- foundation repair. install 18 exterior and 6 interior pilings · 333 m away
- 5504 Colinton AveAug 27, 2025Replacing the pressure regulating valve for my home · 343 m away
- 12550 Harris Branch PkwyMar 2, 2007Skinner nurseries · 344 m away
- 5500 Colinton AveSep 13, 2007Edinburgh gardens sec 2 — edinburgh gardens section two · 363 m away
- 5532 Liberton LnSep 18, 2026Replacement of complete existing central heat and air system with or without duct work · 370 m away
- 12621 Harris Branch PkwyNov 24, 2025Eplan: commercial expedited review - new construction of pad and 40 tall silos for manufacturing process · 371 m away