8408 Shoal Creek Blvd
Austin, TX 78757
Permits cover a temporary Nissan showroom conversion
Austin permits filed from April 7 through June 23, 2026, cover a phased conversion of an existing metal building at 8408 Shoal Creek Blvd into a temporary Nissan showroom. The plans describe a display area, customer lounges, restrooms and sales offices, with later work including mechanical, electrical, plumbing and fire-suppression systems.
Summarized from City of Austin records · updated Jun 23, 2026
- Projects
- 12
- 12 filings
- Latest filing
- Jun 23, 2026
- since Apr 7, 2026
- Largest scope
- —
- Listed value
- —
Where this project stands
Permit active · work underwayPhase 3 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges and sales desk. phase 2 to include mechanical electrical plumbing and fire suppression work
- AppliedJan 27, 2026
- IssuedJun 23, 2026
- WorkJun '26 – Apr '27
- Final inspection
1 contact on this project · 1 phone number
Permit & project history
12 projectsPhase 3 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges and sales desk. phase 2 to include mechanical electrical plumbing and fire suppression work
Phase 3 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges and sales desk. phase 2 to include mechanical electrical plumbing and fire suppression work
City of Austin permitElectrical PermitActive- Record
- 2026-041416 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Phase 1 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices and installation of private fire line. - phase 1 to include interior build out including electrical paint finishes floor finishes lighting interior partitions and mill-work
Phase 1 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices and installation of private fire line. - phase 1 to include interior build out including electrical paint finishes floor finishes lighting interior partitions and mill-work
City of Austin permitPlumbing PermitFinal- Record
- 2026-062019 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Phase 1 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices and installation of private fire line. - phase 1 to include interior build out including electrical paint finishes floor finishes lighting interior partitions and mill-work
Phase 1 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices and installation of private fire line. - phase 1 to include interior build out including electrical paint finishes floor finishes lighting interior partitions and mill-work
City of Austin permitElectrical PermitFinal- Record
- 2026-062018 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Phase 1 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices and installation of private fire line. - phase 1 to include interior build out including electrical paint finishes floor finishes lighting interior partitions and mill-work
Phase 1 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices and installation of private fire line. - phase 1 to include interior build out including electrical paint finishes floor finishes lighting interior partitions and mill-work
City of Austin permitBuilding PermitActive- Record
- 2026-062017 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Phase 2 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices. phase 1 to include structural mechanical electrical plumbing and fire suppression work
Phase 2 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices. phase 1 to include structural mechanical electrical plumbing and fire suppression work
City of Austin permitElectrical PermitFinal- Record
- 2026-041415 EP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Phase 2 - installation of underground fireline with fire riser
Phase 2 - installation of underground fireline with fire riser
City of Austin permitPlumbing PermitFinal- Record
- 2026-045312 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Phase 2 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices. phase 1 to include structural mechanical electrical plumbing and fire suppression work
Phase 2 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices. phase 1 to include structural mechanical electrical plumbing and fire suppression work
City of Austin permitPlumbing PermitFinal- Record
- 2026-046884 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Phase 3 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges and sales desk. phase 2 to include mechanical electrical plumbing and fire suppression work
Phase 3 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges and sales desk. phase 2 to include mechanical electrical plumbing and fire suppression work
City of Austin permitMechanical PermitActive- Record
- 2026-041416 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Phase 2 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices. phase 1 to include structural mechanical electrical plumbing and fire suppression work
Phase 2 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices. phase 1 to include structural mechanical electrical plumbing and fire suppression work
City of Austin permitMechanical PermitFinal- Record
- 2026-041415 MP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Phase 3 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges and sales desk. phase 2 to include mechanical electrical plumbing and fire suppression work
Phase 3 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges and sales desk. phase 2 to include mechanical electrical plumbing and fire suppression work
City of Austin permitPlumbing PermitFinal- Record
- 2026-041416 PP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Phase 3 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges and sales desk. phase 2 to include mechanical electrical plumbing and fire suppression work
Phase 3 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges and sales desk. phase 2 to include mechanical electrical plumbing and fire suppression work
City of Austin permitBuilding PermitActive- Record
- 2026-041416 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Phase 2 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices. phase 1 to include structural mechanical electrical plumbing and fire suppression work
Phase 2 conversion of an existing pre-engineered metal building into a temporary nissan showroom with a display area customer lounges restrooms and sales offices. phase 1 to include structural mechanical electrical plumbing and fire suppression work
City of Austin permitBuilding PermitActive- Record
- 2026-041415 BP
- Tenant / owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 8408 Shoal Creek Blvd
What is being built at 8408 Shoal Creek Blvd?
Austin permit records describe the conversion of an existing metal building into a temporary Nissan showroom, with a display area, customer lounges and sales spaces. The work is planned in phases.
When were permits filed for the showroom at 8408 Shoal Creek Blvd?
The first permits in this set were filed April 7, 2026, and the latest was filed June 23, 2026. The records cover building, electrical, mechanical and plumbing work.
Is a Nissan showroom opening at 8408 Shoal Creek Blvd?
The permit descriptions call for converting the existing building into a temporary Nissan showroom. They do not provide an opening date.
What will the temporary Nissan showroom include?
The permit descriptions include a display area, customer lounges, restrooms and sales offices; a later phase refers to a sales desk. They also describe interior finishes and building systems work.
What are the phases of work at 8408 Shoal Creek Blvd?
Permits describe three phases of conversion. Phase 1 includes interior build-out and a private fire line, while later phases include building systems and fire-suppression work.
What permits cover the 8408 Shoal Creek Blvd conversion?
The City of Austin records include building, electrical, mechanical and plumbing permits filed between April 7 and June 23, 2026. For example, building permits 2026-041415 BP and 2026-041416 BP were filed April 7.
What is being built near Continental Nissan Showroom Remodel?
At 8408 Shoal Creek Blvd, permits describe a phased conversion of an existing building into a temporary Nissan showroom. The Continental Nissan Showroom Remodel is listed nearby at 8406 Shoal Creek Blvd.
Also being built nearby
All of 78757- 8500 Shoal Creek BlvdDec 17, 2025Repair gas line on roof to restore gas service · 110 m away
- 8501 Mopac Expy SvrdMar 2, 2007Reunion park phase 1 · 149 m away
- 8501 N Mopac Expy Svrd NbDec 16, 2025Interior renovation of office in an existing warehouse space with demolition partition mechanical electrical plumbing ceiling finishes and life safety · 149 m away
- 8303 N. Mopac Expy · Ufcu PlazaDec 12, 2024Casa — renovation/alteration — remodel of existing tenant space for new tenant · 177 m away
- 8303 N Mopac Expressway Svrd Nb Barton Skyway 2 100-D · Ufcu A3 & C1May 6, 2024Ufcu a3 & c1 — renovation/alteration — interior alteration of existing restrooms · 177 m away
- 8303 N Mopac Expressway Svrd Nb · University Federal Credit UnionSep 10, 2026Ufcu restroom remodel - b4 & c3 — renovation/alteration — interior alteration of existing core restrooms · 177 m away
- 8303 N. Mopac Expy · Ufcu PlazaMar 31, 2025Ufcu a2 & b2 restrooms — renovation/alteration — interior remodel of existing restrooms · 177 m away
- 8406 Shoal Creek Blvd · Hardeman Family Joint Venture, LtdJan 12, 2026Continental nissan showroom remodel — renovation/alteration — remodel of existing building for use as a temporary nissan showroom · 197 m away
- 8515 Shoal Creek BlvdSep 15, 2026Retroactive permit application for the emergency replacement of two (2) existing 100-gallon commercial water heaters serving the apartment building. at the time of the original service call the existing water heaters were actively leaking and the building had been without hot water for approximately seven business days. due to the active leaks and lack of domestic hot water to the building the condition was classified as an emergency and replacement work proceeded immediately. magic plumbing atx sourced and replaced both existing 100-gallon water heaters and replaced/repaired associated damaged piping and components within the mechanical room as required to complete the installation and restore hot water service. during the work extremely heavy scale/mineral buildup was observed on the hot-water side of the existing system and piping. this application is being submitted retroactively to permit and inspect the completed emergency water-heater replacement work · 206 m away
- 8303 N Mopac Expy Svrd NbSep 30, 2026Interior alteration of existing core restrooms. - [building c-floor 3] · 224 m away
- 8303 Mopac Expy SvrdMar 2, 20078303 mopac driveway addition · 224 m away
- 8500 Millway DrApr 27, 2026Life safety- unable to use bathrooms due to broken cast iron will need to redo pvc under slab · 245 m away