5904 Spartan Cv
Austin, TX 78759
Drain-line repair permitted at 5904 Spartan Cv
A plumbing permit filed September 15, 2026, covers work on the main drain line at 5904 Spartan Cv in Austin. The permit describes creating a 2-by-2-foot access opening by the hall bathroom and tunneling 12 to 15 feet to correct the drain line’s fall and support it with clevis hangers.
Summarized from City of Austin records · updated Sep 15, 2026
- Projects
- 1
- 1 filings
- Latest filing
- Sep 15, 2026
- since Sep 15, 2026
- Largest scope
- —
- Listed value
- —
Where this project stands
FinaledCreate a access hole by the hall bathroom 2 foot by 2 foot hole will be made and tunnel under 12 to 15 feet to correct fall on the main drain line and support with clevis hangers
- AppliedSep 13, 2026
- IssuedSep 15, 2026
- WorkSep '26 – Sep '26
- Final inspectionSep 23, 2026
Passed final inspection Sep 23, 2026.
1 contact on this project · 1 phone number
Permit & project history
1 projectCreate a access hole by the hall bathroom 2 foot by 2 foot hole will be made and tunnel under 12 to 15 feet to correct fall on the main drain line and support with clevis hangers
Create a access hole by the hall bathroom 2 foot by 2 foot hole will be made and tunnel under 12 to 15 feet to correct fall on the main drain line and support with clevis hangers
City of Austin permitPlumbing PermitFinal- Record
- 2026-120140 PP
- Owner
- Pro
- Contractor
- Pro
- Contact
- Pro
Sources: City of Austin
Questions about 5904 Spartan Cv
What is being built at 5904 Spartan Cv?
The permit describes a main drain-line repair, not a new building. The work includes an access opening near the hall bathroom and a tunnel beneath the floor.
What work is planned at 5904 Spartan Cv in Austin?
Permit 2026-120140 PP covers creating a 2-by-2-foot access hole and tunneling 12 to 15 feet to correct the fall of the main drain line and support it with clevis hangers.
When was the plumbing permit filed for 5904 Spartan Cv?
The City of Austin permit was filed September 15, 2026. The record lists its status as Final.
Is a new home being built at 5904 Spartan Cv?
The available permit record describes plumbing work on a main drain line, not construction of a new home.
How much will the drain-line repair at 5904 Spartan Cv cost?
The permit record does not list a project cost or reported valuation.
Also being built nearby
All of 78759- 5902 Spartan CvJan 13, 2026Sb 1202 home back up installation - battery · 34 m away
- 9400 Bluegrass DrJun 10, 2026Express: replace 1 existing window - size for size replace 1 existing door - size for size double window at garage only · 110 m away
- 9409 Bluegrass DrNov 25, 2024Replace an existing optional standby generator automatic transfer switch and a docking station on new concrete equipment pad for existing fs33 · 138 m away
- 9308 Bluegrass DrApr 10, 2026(goldenberg marius) - installation of circuit for elec. vehicle charging station - esip · 145 m away
- 5828 Linaria LnMay 22, 2026200-amp underground service rebuild · 166 m away
- 9347 Simmons RdSep 28, 2026Replacement of an existing water heater removing existing tankless water heater in attic and installing new tankless water heater in attic · 172 m away
- 9342 Simmons RdNov 3, 2025Installation of a 240 volt 50 amp circuit for a tesla wall connector ev charging unit set for a 40 amp charge rate · 186 m away
- 9304 Bluegrass DrSep 2, 2025Install generac 26kw and 200 amp ats to existing electrical service to a stand alone propane tank...the tank to the generator only · 188 m away
- 9317 Bluegrass DrApr 4, 2024Express replace 18 existing windows · 197 m away
- 9313 Bluegrass DrSep 28, 2026Replacement of complete existing central heat and air system with or without duct work · 213 m away
- 9540 Ketona CvJun 6, 2024Replacement of complete existing central heat and air system with or without duct work · 217 m away
- 9309 Bluegrass DrSep 4, 2025Controlled outage upgrading meter base and panel from 125 to 200 amps replacing main subpanel outside installing additional ground rod installing gm energy home hub/gateway as main service equipment with 200 amp main breaker moving bonding into gateway and installing bi-directional ev charger for whole home energy back up · 230 m away