Bedford Fire Station 2 renovation and addition
A renovation and addition to the existing Bedford Fire Station 2 at 3940 Martin Drive was registered with the Texas Department of Licensing and Regulation on May 6, 2025. The project description calls for new interior finishes and site work at the existing 4,552-square-foot station. The applicant estimates the project cost at $3 million.
Summarized from Texas Department of Licensing and Regulation records · updated May 6, 2025
- Projects
- 1
- 1 filings
- Latest filing
- May 6, 2025
- since May 6, 2025
- Largest scope
- 6,390 sf
- Estimated cost
- $3.0M
- state registration
Where this project stands
Finishing up · inspection nextBedford Fire Station 2 Addition & Renovation
6,390 sq ft · $3.0M est.
- RegisteredMay 6, 2025
- Plan review
- ConstructionJun '25 – Jul '26
- Inspectednow
- Closed
Scheduled to finish Jul 15, 2026; the state inspection hasn't been filed yet.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectThe renovation and addition of an existing 4,552sf fire station to include all new interior finishes and site work — bedford fire station 2
TDLR project registrationAdditions to Existing BuildingReview Complete6,390 sq ft$3.0M est.- Project #
- TABS2025018271
- Tenant / owner
- Bedford Fire Station 2 Addition & Renovation
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 3940 Martin Drive
What is being built at 3940 Martin Drive in Bedford?
The project is an addition and renovation to Bedford Fire Station 2, an existing 4,552-square-foot fire station. The description includes new interior finishes and site work.
Is Bedford Fire Station 2 being renovated?
Yes. A TDLR project registration dated May 6, 2025, describes an addition and renovation to the existing station.
When was the Bedford Fire Station 2 project filed?
The project was registered with the Texas Department of Licensing and Regulation on May 6, 2025. Its TDLR status is listed as Review Complete.
How large is the Bedford Fire Station 2 project?
The TDLR registration lists 6,390 square feet for the project. Its description identifies the existing fire station as 4,552 square feet.
How much will the Bedford Fire Station 2 renovation cost?
The applicant's estimated cost for the project is $3 million.
Who is behind the Bedford Fire Station 2 addition and renovation?
The project record names the City of Bedford and describes work at Bedford Fire Station 2.