groundranger
Historic · latest filing Feb 2025Commercial

2995 US Hwy 90 W

Castroville, TX 78009 · Microsoft Corporation

Two data center buildings planned at 2995 US Hwy 90 W

A TDLR project registration describes two single-story data center buildings, each containing five colos, plus associated campus site construction at 2995 US Hwy 90 W. The registration was filed February 25, 2025, and describes approximately 489,400 square feet of gross building area.

Summarized from Texas Department of Licensing and Regulation records · updated Feb 25, 2025

Projects
1
1 filings
Latest filing
Feb 25, 2025
since Feb 25, 2025
Largest scope
489,400 sf
Estimated cost
$765M
state registration

Where this project stands

Under construction

SAT89/90 Data Center

489,400 sq ft · $765M est.

  1. RegisteredFeb 25, 2025
  2. Plan review
  3. ConstructionJun '25 – Jul '27
  4. Inspected
  5. Closed
68% through of a 26-month buildJun 1, 2025 → Jul 31, 2027

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. SAT89/90 Data Center

    Construction of two single-story data center buildings each containing five colos, plus associated campus site construction. approximately 489,400 square feet gross building area. — sat89/90 data center

    TDLR project registrationNew ConstructionReview Complete489,400 sq ft$765M est.
    Tenant / owner
    Sat89/90 Data Center
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 2995 US Hwy 90 W

What is being built at 2995 US Hwy 90 W in Castroville?

A TDLR registration describes two single-story data center buildings, each with five colos, plus associated campus site construction. The project is named SAT89/90 Data Center.

When was the SAT89/90 Data Center project registered?

The TDLR project registration was filed February 25, 2025. Its status is listed as Review Complete.

How large is the SAT89/90 Data Center project?

The registration describes approximately 489,400 square feet of gross building area across the two buildings.

How many buildings are planned for the Castroville data center?

The registration describes two single-story data center buildings, each containing five colos.

How much is the SAT89/90 Data Center expected to cost?

The TDLR registration lists an estimated project cost of $765 million. This is the applicant’s estimate for the project.

Email me when it passes inspection