TDLR records list data center construction in Cedar Creek

Two TDLR project registrations describe new construction of a 576,777-square-foot data center with supporting office space and site improvements at 6543 FM 535. The registrations were filed August 21 and 24, 2026; each lists an estimated project cost of $700 million.

Summarized from Texas Department of Licensing and Regulation records · updated Aug 24, 2026

Projects
2
2 filings
Latest filing
Aug 24, 2026
since Aug 21, 2026
Largest scope
577,000 sf
Estimated cost
$700M
state registration

Where this project stands

In state plan review

EDCAUS32

577,000 sq ft · $700M est.

  1. RegisteredAug 24, 2026
  2. Plan reviewnow
  3. ConstructionOct '26 – Dec '28
  4. Inspected
  5. Closed

Design is filed with the state. Subcontractors and suppliers are usually picked around now.

4 contacts on this project · 3 phone numbers

Permit & project history

2 projects
  1. EDCAUS32

    New construction of a 576,777 sq ft 1-story data center with supporting office space and associated site improvements. the building is designed to be a type ii-b construction classification and will be fully protected by an automatic sprinkler system. — edcaus32

    TDLR project registrationNew ConstructionProject Registered577,000 sq ft$700M est.
    Tenant / owner
    Pro
    Design firm
    Pro
    Contact
    Pro
  2. EDCAUS31

    New construction of a 576,777 sq ft 1-story data center with supporting office space and associated site improvements. the building is designed to be a type ii-b construction classification and will be fully protected by an automatic sprinkler system — edcaus31

    TDLR project registrationNew ConstructionProject Registered577,000 sq ft$700M est.
    Tenant / owner
    Pro
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 6543 FM 535

What is being built at 6543 FM 535 in Cedar Creek?

TDLR records describe new construction of a data center with supporting office space and associated site improvements. The two registrations are named EDCAUS31 and EDCAUS32.

How large is the data center planned for 6543 FM 535?

Each registration describes a 576,777-square-foot, one-story data center.

When were the data center projects registered?

TDLR project TABS2026028550 was registered August 21, 2026, and TABS2026028609 was registered August 24, 2026.

How many data center projects are listed at 6543 FM 535?

The records show two TDLR project registrations, both describing new construction of a 576,777-square-foot data center.

What is the estimated cost of the data center project?

Each TDLR registration lists an estimated project cost of $700 million. This is the applicant's estimate in the registrations.

More offices in 78612.

Email me when plan review is complete