groundranger
Historic · latest filing Mar 2024Commercial

1215 Toro Grande Blvd

Cedar Park, TX 78613 · Vasda Developers LLC

Toro Grande shared infrastructure planned in Cedar Park

A master infrastructure project at 1215 Toro Grande Blvd includes a water-quality feature, a detention pond, about 495 feet of shared access drive aisle, and a driveway connection to Toro Grande Boulevard. The project was registered with TDLR on March 12, 2024; its status is listed as inspection complete, and the applicant estimated its cost at $1 million.

Summarized from Texas Department of Licensing and Regulation records · updated Mar 12, 2024

Projects
1
1 filings
Latest filing
Mar 12, 2024
since Mar 12, 2024
Largest scope
100,000 sf
Estimated cost
$1.0M
state registration

Where this project stands

Inspected · closing out

Toro Grande Shared Improvements

100,000 sq ft · $1.0M est.

  1. RegisteredMar 12, 2024
  2. Plan review
  3. ConstructionNov '24 – Nov '25
  4. Inspected
  5. Closednow

The building is substantially done. Move-in, fit-out and service work usually follow.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Master infrastructure to include water quality and detention pond, +/-495 lf shared access drive aisle, and driveway connection to toro grande blvd. — na

    TDLR project registrationNew ConstructionInspection Complete100,000 sq ft$1.0M est.
    Tenant / owner
    Toro Grande Shared Improvements
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 1215 Toro Grande Blvd

What is being built at 1215 Toro Grande Blvd in Cedar Park?

The TDLR registration describes master infrastructure, including a water-quality feature, a detention pond, about 495 feet of shared access drive aisle, and a driveway connection to Toro Grande Boulevard. The project was registered on March 12, 2024.

Is a new building planned at 1215 Toro Grande Blvd?

The available TDLR record describes shared infrastructure, not a new building. It lists the project as new construction and gives a status of inspection complete.

What is the Toro Grande Shared Improvements project?

It is a TDLR-registered project for master infrastructure at 1215 Toro Grande Blvd, including drainage-related features, shared access, and a driveway connection. Its registration number is TABS2024013583.

How much will the Toro Grande infrastructure project cost?

The TDLR registration lists an applicant-estimated project cost of $1 million. This is an estimate, not a confirmed final cost.

Is the Toro Grande Shared Improvements project complete?

The TDLR record lists the project status as inspection complete. The record was filed on March 12, 2024.