Active · latest filing Sep 2026Commercial

525 A Co Rd

Childress, TX 79201 · Childress Dc1, LLC

806,359-square-foot data center registered in Childress

A single-story data center with office space and associated support areas is planned at 525 A Co Rd in Childress. The Texas Department of Licensing and Regulation registered the new-construction project on September 11, 2026. The registration lists 806,359 square feet and an applicant-estimated project cost of $2.4 billion.

Summarized from Texas Department of Licensing and Regulation records · updated Sep 11, 2026

Projects
1
1 filings
Latest filing
Sep 11, 2026
since Sep 11, 2026
Largest scope
806,359 sf
Estimated cost
$2400M
state registration

Where this project stands

In state plan review

Project Hyper - Childress

806,359 sq ft · $2400M est.

  1. RegisteredSep 11, 2026
  2. Plan reviewnow
  3. ConstructionJul '26 – Feb '28
  4. Inspected
  5. Closed

Design is filed with the state. Subcontractors and suppliers are usually picked around now.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. Project Hyper - Childress

    Single story data center including office space, multiple data centers and associated support spaces. total area of building: 806,359 sq ft — childress building 1

    TDLR project registrationNew ConstructionProject Registered806,359 sq ft$2400M est.
    Tenant / owner
    Project Hyper - Childress
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 525 A Co Rd

What is being built at 525 A Co Rd in Childress?

A TDLR registration describes a single-story data center with office space, multiple data centers and associated support areas. It lists the project as new construction.

How large is the Childress data center project?

The TDLR registration lists a total building area of 806,359 square feet.

When was the Childress data center project registered?

The project was registered with the Texas Department of Licensing and Regulation on September 11, 2026.

How much is the Childress data center expected to cost?

The TDLR registration lists an applicant-estimated project cost of $2.4 billion.

Is the data center project listed as new construction?

Yes. The TDLR project registration, TABS2027000824, lists the work type as new construction.

Does the Childress data center include office space?

Yes. The project description includes office space, multiple data centers and associated support areas.