Drainage and pavement work registered at Cibolo Valley Elementary
A project at Cibolo Valley Elementary calls for replacing concrete flatwork and asphalt pavement and installing sidewalks and trench drains. The Texas Department of Licensing and Regulation registration was filed April 8, 2024, and lists the project as closed. The applicant’s estimated project cost is $990,000.
Summarized from Texas Department of Licensing and Regulation records · updated Apr 8, 2024
- Projects
- 1
- 1 filings
- Latest filing
- Apr 8, 2024
- since Apr 8, 2024
- Largest scope
- 5,400 sf
- Estimated cost
- $990K
- state registration
Where this project stands
CompletedCV Drainage and Soil Improvement
5,400 sq ft · $990K est.
- RegisteredApr 8, 2024
- Plan review
- ConstructionMay '24 – Jul '24
- Inspected
- Closed
Ran as a 2-month build.
4 contacts on this project · 2 phone numbers
Permit & project history
1 projectSelect demolition of concrete flatwork and asphalt pavement. installation of new concrete flatwork and asphalt pavement. installation of sidewalks. installation of trench drains. — cibolo valley elementary
TDLR project registrationRenovation/AlterationProject Closed5,400 sq ft$990K est.- Project #
- TABS2024015666
- Tenant / owner
- Cv Drainage And Soil Improvement
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 4093 Green Valley Rd
What is being built at 4093 Green Valley Rd in Cibolo?
The registered project describes site improvements at Cibolo Valley Elementary: new concrete flatwork and asphalt pavement, sidewalks, and trench drains, following selective demolition of existing pavement.
Is a new school being built at 4093 Green Valley Rd?
The TDLR record describes renovation and site improvements at Cibolo Valley Elementary, not construction of a new school building.
When was the Cibolo Valley Elementary project filed?
The TDLR project registration was filed April 8, 2024. Its project number is TABS2024015666.
What work is planned at Cibolo Valley Elementary?
The registration describes selective demolition of concrete flatwork and asphalt pavement, followed by installation of new concrete flatwork, asphalt pavement, sidewalks, and trench drains.
How much is the Cibolo Valley Elementary project estimated to cost?
The applicant’s TDLR estimate is $990,000 for the project.
Is the Cibolo Valley Elementary project still active?
The TDLR record lists the project status as closed.