17944 Highway 242
Conroe, TX 77300 · Storage King - Building 9, Storage King Office-Warehouse
Two Storage King projects registered at 17944 Highway 242
TDLR records indicate new construction for Storage King at 17944 Highway 242: two one-story office-warehouse buildings and a separate one-story climatized building. The office-warehouse project was registered on March 27, 2026, and the Building 9 project was registered on September 17, 2026.
Summarized from Texas Department of Licensing and Regulation records · updated Sep 17, 2026
- Projects
- 2
- 2 filings
- Latest filing
- Sep 17, 2026
- since Mar 27, 2026
- Largest scope
- 41,915 sf
- Estimated cost
- $4.1M
- state registration
Where this project stands
In state plan reviewStorage King - Building 9
36,200 sq ft · $2.9M est.
- RegisteredSep 17, 2026
- Plan reviewnow
- ConstructionJan '27 – Jan '28
- Inspected
- Closed
Construction is scheduled to start Jan 30, 2027. Subcontractors and suppliers are usually picked in the weeks before.
4 contacts on this project · 3 phone numbers
Permit & project history
2 projects(1) 1-story climatized building with slab-on-grade foundation, metal wall panels over metal studs, and metal roof. site work to include paving. — storage king - building 9
TDLR project registrationNew ConstructionProject Registered36,200 sq ft$2.9M est.- Project #
- TABS2027001260
- Tenant / owner
- Storage King - Building 9
- Design firm
- Pro
- Contact
- Pro
(2) 1-story buildings with slab on grade foundation, metal stud construction with metal wall panels and stone veneer. work will include foundation, mechanical, electrical and plumbing. — storage king office-warehouse
TDLR project registrationNew ConstructionReview Complete41,915 sq ft$4.1M est.- Project #
- TABS2026016105
- Tenant / owner
- Storage King Office-Warehouse
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 17944 Highway 242
What is being built at 17944 Highway 242?
TDLR records list two Storage King projects: two one-story office-warehouse buildings and a separate one-story climatized building called Building 9.
How many buildings are planned at the Storage King site?
The registrations describe three buildings in total: two office-warehouse buildings and one climatized building.
How large are the Storage King projects?
The office-warehouse project is listed at 41,915 square feet. Building 9 is listed at 36,200 square feet.
When were the Storage King projects registered?
The office-warehouse project was registered on March 27, 2026. Building 9 was registered on September 17, 2026.
What are the buildings made of?
The office-warehouse plans describe metal-stud construction with metal wall panels and stone veneer. Building 9 is described with metal wall panels over metal studs and a metal roof.
What is the status of the Storage King construction projects?
TDLR lists the office-warehouse project as “Review Complete” and Building 9 as “Project Registered.”