Central Counties Services renovation planned in Copperas Cove
A renovation for Central Counties Services’ Copperas Cove facility was registered with the Texas Department of Licensing and Regulation on September 29, 2025. The 11,700-square-foot project includes interior work, replacement of exterior materials, and resealing and restriping the parking lot; the applicant’s estimated cost is $1.5 million.
Summarized from Texas Department of Licensing and Regulation records · updated Sep 29, 2025
- Projects
- 1
- 1 filings
- Latest filing
- Sep 29, 2025
- since Sep 29, 2025
- Largest scope
- 11,700 sf
- Estimated cost
- $1.5M
- state registration
Where this project stands
Finishing up · inspection nextCentral Counties Services - Copperas Cove Facility
11,700 sq ft · $1.5M est.
- RegisteredSep 29, 2025
- Plan review
- ConstructionDec '25 – Oct '26
- Inspectednow
- Closed
Scheduled to finish Oct 1, 2026; the state inspection hasn't been filed yet.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectInterior renovation of 9800 sq ft remainder of building to be complete in a future tenant finish out. remove and replace all exterior materials. reseal and restripe the entire parking lot. — ccs - copperas cove facility
TDLR project registrationRenovation/AlterationReview Complete11,700 sq ft$1.5M est.- Project #
- TABS2026002089
- Tenant / owner
- Central Counties Services - Copperas Cove Facility
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 1012 North Drive
What is being built at 1012 North Drive in Copperas Cove?
A TDLR registration describes a renovation for Central Counties Services’ Copperas Cove facility, including interior work, exterior material replacement, and parking lot work. It was registered September 29, 2025, under project number TABS2026002089.
Is Central Counties Services opening a new facility at 1012 North Drive?
The available record describes renovation work at the Central Counties Services – Copperas Cove Facility, not a new facility. The registration was filed September 29, 2025.
What renovation work is planned at the Copperas Cove facility?
The registration lists interior renovation of 9,800 square feet, replacement of exterior materials, and resealing and restriping the parking lot. It identifies the full project as 11,700 square feet.
When was the 1012 North Drive project registered?
The Texas Department of Licensing and Regulation registration is dated September 29, 2025. The project number is TABS2026002089.
How much will the Central Counties Services renovation cost?
The applicant’s estimated cost for the project is $1.5 million. This is an estimate in the TDLR registration.
Is the interior renovation at 1012 North Drive complete?
The registration says the remaining 9,800 square feet is to be completed in a future tenant finish-out. It does not provide a completion date.