groundranger
Historic · latest filing Apr 2024Commercial

302 W. 10th Street

Crane, TX 79731 · Crane ISD

Crane ISD middle school addition and renovation

Crane ISD registered plans for a middle school addition and renovation at 302 W. 10th Street on April 26, 2024. The project describes 55,000 square feet of new construction and 10,000 square feet of renovations, including a single-story education and administration wing and a gym. The applicant estimated the project cost at $41.75 million.

Summarized from Texas Department of Licensing and Regulation records · updated Apr 26, 2024

Projects
1
1 filings
Latest filing
Apr 26, 2024
since Apr 26, 2024
Largest scope
65,000 sf
Estimated cost
$42M
state registration

Where this project stands

Inspected · closing out

CRANE ISD MIDDLE SCHOOL ADDITION AND RENOVATION

65,000 sq ft · $42M est.

  1. RegisteredApr 26, 2024
  2. Plan review
  3. ConstructionMay '24 – Jul '26
  4. Inspected
  5. Closednow

The building is substantially done. Move-in, fit-out and service work usually follow.

4 contacts on this project · 3 phone numbers

Permit & project history

1 project
  1. New construction and renovation to the existing facility. the new, single story, middle school will consist of an education and administration wing located on the west side, along with a new gym on the east side. 55,000 new and 10,000 reno sq ft — crane middle school

    TDLR project registrationRenovation/AlterationInspection Complete65,000 sq ft$42M est.
    Tenant / owner
    Crane ISD Middle School Addition And Renovation
    Design firm
    Pro
    Contact
    Pro

Sources: Texas Department of Licensing and Regulation

Questions about 302 W. 10th Street

What is being built at 302 W. 10th Street in Crane?

Crane ISD registered plans for a middle school addition and renovation. The plans describe a new education and administration wing and a gym, along with renovations to the existing facility.

When was the Crane ISD middle school project filed?

The TDLR project registration was filed April 26, 2024. Its project number is TABS2024017126.

How large is the Crane middle school project?

The registration describes 55,000 square feet of new construction and 10,000 square feet of renovation, for 65,000 square feet total.

What will the new middle school building include?

The plans describe a single-story education and administration wing on the west side and a new gym on the east side.

How much is the Crane ISD middle school project estimated to cost?

The applicant's TDLR estimate is $41.75 million. This is an estimate for the project, not a reported final cost.

What school project is planned near Crane ISD at 509 W. 8th Street?

At 302 W. 10th Street, Crane ISD registered plans for a middle school addition and renovation on April 26, 2024. The registration lists the project status as inspection complete.