Crowley 9th Grade Center cafeteria and restroom renovations
A 5,100-square-foot renovation at Crowley ISD’s Crowley 9th Grade Center was registered with TDLR on May 17, 2024. The work includes renovating the cafeteria and older group restrooms for accessibility, removing a platform and replacing some finishes. The applicant’s estimated project cost is $2,158,446, and the registration lists the project as inspection complete.
Summarized from Texas Department of Licensing and Regulation records · updated May 17, 2024
- Projects
- 1
- 1 filings
- Latest filing
- May 17, 2024
- since May 17, 2024
- Largest scope
- 5,100 sf
- Estimated cost
- $2.2M
- state registration
Where this project stands
Inspected · closing outADDS RENOVS & SITE IMPR. AT CROWLEY 9TH GR
5,100 sq ft · $2.2M est.
- RegisteredMay 17, 2024
- Plan review
- ConstructionJul '24 – Dec '25
- Inspected
- Closednow
The building is substantially done. Move-in, fit-out and service work usually follow.
4 contacts on this project · 3 phone numbers
Permit & project history
1 projectCrowly 9th grade campus. remove platform and renovate cafeteria. renovate old group restrooms for accessibility. replace some finishes. — crowley 9th grade center
TDLR project registrationRenovation/AlterationInspection Complete5,100 sq ft$2.2M est.- Project #
- TABS2024018833
- Tenant / owner
- Adds Renovs & Site Impr. At Crowley 9th Gr
- Design firm
- Pro
- Contact
- Pro
Sources: Texas Department of Licensing and Regulation
Questions about 1016 Fm1187
What is being built at 1016 FM 1187 in Crowley?
The project is a renovation at Crowley ISD’s Crowley 9th Grade Center, not a new building. Plans include cafeteria and restroom renovations, platform removal and finish replacements.
What renovations are planned at Crowley 9th Grade Center?
The work includes renovating the cafeteria, renovating older group restrooms for accessibility, removing a platform and replacing some finishes.
When was the Crowley 9th Grade Center project permitted?
The TDLR project registration was filed May 17, 2024. The record is TABS2024018833.
How much will the Crowley 9th Grade Center renovation cost?
The applicant’s estimated cost for the project is $2,158,446. This is an estimate listed in the TDLR registration.
Is the Crowley 9th Grade Center renovation complete?
The TDLR registration lists the project status as inspection complete.
How large is the Crowley 9th Grade Center renovation?
The TDLR registration lists the project area as 5,100 square feet.